2349 S PROSSER AVE 90064
Certificate Information: 2349 S PROSSER AVE 90064
- Application / Permit
- 19014-30000-07210
- Plan Check / Job No.
- B19WL07382
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2nd floor addition (157 sf) to (e) 2-story SFD
- Permit Issued
- Issued on 5/26/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | REZA HAGHIGHAT |
| Green Plans Picked Up | 2/20/2020 | APPLICANT |
| Corrections Issued | 2/24/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 3/6/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 3/13/2020 | APPLICANT |
| Applicant returned to address corrections | 4/15/2021 | REZA HAGHIGHAT |
| Plan Check Approved | 4/26/2021 | REZA HAGHIGHAT |
| Issued | 5/26/2021 | APPLICANT |
| CofO in Progress | 7/1/2022 | EVAN COOPER |
| Permit Finaled | 7/11/2022 | DANIEL ORRANTE |
| CofO Issued | 7/11/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/11/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/9/2020 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 3/24/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 3/24/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | ANTHONY MAINEZ |
| Green Code | Cleared | 4/26/2021 | RICHARD GARCIA |
Contact Information
| Architect | Fonda-Bonardi,, Mario; Lic. No.: C11271 | 1450 23RD STREET SANTA MONICA, CA 904042902 |
| Contractor | Malekmanesh Kamyar; Lic. No.: 604814-B | 4162 WOODCLIFF ROAD SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/16/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Barrier | 7/16/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 7/16/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 7/22/2021 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 8/10/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 8/10/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 9/3/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 9/3/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 9/3/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 9/14/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 9/14/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Insulation | 9/14/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/14/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 9/16/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 9/16/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 9/16/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 9/16/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 9/21/2021 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/21/2021 | Partial Approval | CHRISTOPHER WILSON |
| Wood Frame | 9/21/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 9/28/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 9/28/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 9/28/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 5/13/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 5/13/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 5/13/2022 | SGSOV Approved | BRENDAN LOONEY |
| Smoke Detectors | 5/13/2022 | Approved | BRENDAN LOONEY |
| Final | 7/5/2022 | OK to Issue CofO | EVAN COOPER |