609 S MANSFIELD AVE 90036

Certificate Information: 609 S MANSFIELD AVE 90036

Application / Permit
19014-30000-07166
Plan Check / Job No.
B19WL07360
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2nd floor addition and interior remodel to (E) 1 story SFD.
Permit Issued
Issued on 3/26/2022
Issuing Office
Current Status
CofO Issued on 6/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 1/6/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 1/22/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/31/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 6/5/2020 APPLICANT
Plan Check Approved 6/15/2020 VLADIMIR ARUTYUNYAN
Issued 3/26/2022 APPLICANT
Building Plans Picked Up 3/31/2022 APPLICANT
CofO in Progress 5/30/2024 RONNIE MINDANAO
Permit Finaled 6/27/2024 DEROLD HAUFF
CofO Issued 6/27/2024 DEROLD HAUFF
Permit Finaled 6/27/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/19/2020 THOMAS LANG
Permit Cleared 2/19/2020 THOMAS LANG
Sewer availability Cleared 2/19/2020 THOMAS LANG
Low Impact Development Cleared 2/27/2020 ORVAL HERNANDEZ-MARCIAL
Green Code Cleared 3/5/2020 DONALD CRICHLOW
Roof/Waste drainage to street Cleared 3/5/2020 DENNIS BRAGIN

Contact Information

Architect Park,, Sang Hun; Lic. No.: C33387 1424 4TH ST. #700B      SANTA MONICA, CA 90401
Contractor Mek Air Tech; Lic. No.: 645909-B 609 S MANSFIELD AVE      LOS ANGELES, CA 90036
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/26/2022 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 12/30/2022 Partial Approval RICHARD DOCKUS
Footing/Foundation/Slab 2/27/2023 Not Ready for Inspection RICHARD DOCKUS
METHANE-Barrier 2/27/2023 Not Ready for Inspection RICHARD DOCKUS
METHANE-Subgrade 2/27/2023 Not Ready for Inspection RICHARD DOCKUS
Footing/Foundation/Slab 3/1/2023 Partial Approval RICHARD DOCKUS
METHANE-Barrier 3/1/2023 Approved RICHARD DOCKUS
METHANE-Subgrade 3/1/2023 Approved RICHARD DOCKUS
Footing/Foundation/Slab 3/17/2023 Partial Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 6/7/2023 Approved RICHARD DOCKUS
Footing/Foundation/Slab 6/7/2023 Approved RICHARD DOCKUS
Pre-Inspection 6/30/2023 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 7/18/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 7/18/2023 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 7/21/2023 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 8/2/2023 Partial Approval LILIANA PORTILLO
Insulation 8/2/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 9/1/2023 Approved ROY SPAULDING
PLUMBING-Rough 9/1/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 9/6/2023 Approved ROY SPAULDING
Green Building Rough 9/6/2023 Approved ROY SPAULDING
METHANE-Rough 9/6/2023 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 9/13/2023 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Approved RICHARD DOCKUS
Gas Test 10/25/2023 Approved ROY SPAULDING
PLUMBING-Rough 10/25/2023 Approved ROY SPAULDING
HVAC-Rough 10/27/2023 Corrections Issued DAVID FEILER
Wood Frame 10/31/2023 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 11/3/2023 Approved RICHARD DOCKUS
HVAC-Rough 11/3/2023 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 11/6/2023 Partial Approval RICHARD DOCKUS
HVAC-Rough 11/6/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 11/9/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 12/4/2023 Corrections Issued RICHARD DOCKUS
Interior/Exterior Lathing 12/7/2023 Partial Approval RICHARD DOCKUS
Insulation 12/19/2023 Approved LILIANA PORTILLO
Drywall Nailing 12/29/2023 Partial Approval RICHARD DOCKUS
Drywall Nailing 1/8/2024 Approved RICHARD DOCKUS
Interior/Exterior Lathing 2/7/2024 Corrections Issued AMIR NAZARIAN
Interior/Exterior Lathing 2/9/2024 Approved RICHARD DOCKUS
HVAC-Final 3/28/2024 Not Ready for Inspection RONNIE MINDANAO
HVAC-Final 4/15/2024 Approved RONNIE MINDANAO
PLUMBING-Final 4/17/2024 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Final 4/22/2024 Corrections Issued RONNIE MINDANAO
PLUMBING-Final 4/22/2024 Corrections Issued RONNIE MINDANAO
ELECTRICAL-Final 4/24/2024 Approved RONNIE MINDANAO
Final 4/24/2024 Corrections Issued RONNIE MINDANAO
Green Building Final 4/24/2024 Approved RONNIE MINDANAO
PLUMBING-Final 4/24/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Approved RONNIE MINDANAO
Smoke Detectors 4/24/2024 Approved RONNIE MINDANAO
Final 4/29/2024 Not Ready for Inspection ROY SPAULDING
Final 5/2/2024 Not Ready for Inspection RONNIE MINDANAO
Final 5/8/2024 Not Ready for Inspection RONNIE MINDANAO
Final 5/29/2024 OK to Issue CofO RONNIE MINDANAO