Excavation/Setback/Form/Re-Bar
|
1/13/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
1/13/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
METHANE-Barrier
|
1/13/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
METHANE-Subgrade
|
1/13/2021
|
Approved
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
1/14/2021
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
METHANE-Rough
|
1/14/2021
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
2/16/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
2/16/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
METHANE-Rough
|
2/16/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Reinforced Concrete Frame
|
2/16/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/23/2021
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Footing/Foundation/Slab
|
2/23/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Barrier
|
2/23/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Excavation/Setback/Form/Re-Bar
|
2/24/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Methane Barrier
|
4/21/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
4/21/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
METHANE-Barrier
|
4/21/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
METHANE-Final
|
4/21/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
METHANE-Rough
|
4/21/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Underground Mechanical
|
4/21/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
METHANE-Subgrade
|
4/23/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Underground Mechanical
|
4/23/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Rough
|
4/26/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Underground Mechanical
|
4/26/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Methane Barrier
|
5/6/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Footing/Foundation/Slab
|
5/11/2021
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Barrier
|
5/11/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Subgrade
|
5/11/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Footing/Foundation/Slab
|
5/13/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Barrier
|
5/13/2021
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Final
|
5/13/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Rough
|
5/13/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Subgrade
|
5/13/2021
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Footing/Foundation/Slab
|
6/21/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Drilled-In Anchors
|
6/22/2021
|
No Access for Inspection
|
ADAM ESCOTO
|
|
Deputy Drilled-In Anchors
|
7/27/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Underground Mechanical
|
8/2/2021
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Wood Frame
|
8/2/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/5/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
8/5/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Wood Construction
|
9/1/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/2/2021
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Drilled-In Anchors
|
10/8/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Excavation/Setback/Form/Re-Bar
|
10/21/2021
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Footing/Foundation/Slab
|
10/21/2021
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Masonry Wall/Backfill
|
10/21/2021
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Reinforced Masonry Frame
|
10/21/2021
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
PLUMBING-Rough
|
11/12/2021
|
Approved
|
BRENDAN LOONEY
|
|
HVAC-Rough
|
12/1/2021
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Special/Order Compliance
|
12/1/2021
|
Corrections Issued
|
BRENDAN LOONEY
|
|
ELECTRICAL-Rough
|
12/2/2021
|
Partial Inspection
|
BRENDAN LOONEY
|
|
ELECTRICAL-Rough
|
12/6/2021
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Excavation/Setback/Form/Re-Bar
|
12/6/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Footing/Foundation/Slab
|
12/6/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Green Building Rough
|
12/6/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
METHANE-Rough
|
12/6/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Reinforced Concrete Frame
|
12/6/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
ELECTRICAL-Rough
|
12/8/2021
|
Approved
|
BRENDAN LOONEY
|
|
HVAC-Rough
|
12/8/2021
|
Conditional Approval
|
BRENDAN LOONEY
|
|
Special/Order Compliance
|
12/8/2021
|
Partial Inspection
|
MICHAEL PELHAM
|
|
Deputy Wood Construction
|
2/25/2022
|
Approved
|
MICHAEL PELHAM
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/25/2022
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
BUILDING-Rough-Frame
|
4/5/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Green Building Rough
|
4/5/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
BUILDING-Rough-Frame
|
4/7/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/7/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Shower Pan
|
4/7/2022
|
Approved
|
BRENDAN LOONEY
|
|
Special/Order Compliance
|
4/7/2022
|
Partial Inspection
|
MICHAEL PELHAM
|
|
Insulation
|
4/20/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
Interior/Exterior Lathing
|
5/3/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
5/3/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
5/12/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Green Building Rough
|
5/12/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
METHANE-Rough
|
5/12/2022
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
BUILDING-Rough-Frame
|
5/18/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Green Building Rough
|
5/18/2022
|
Approved
|
BRENDAN LOONEY
|
|
HVAC-Rough
|
5/18/2022
|
Approved
|
BRENDAN LOONEY
|
|
METHANE-Rough
|
5/18/2022
|
Approved
|
BRENDAN LOONEY
|
|
Sewer
|
5/18/2022
|
Approved
|
BRENDAN LOONEY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/23/2022
|
Approved
|
BRENDAN LOONEY
|
|
Insulation
|
5/23/2022
|
Approved
|
BRENDAN LOONEY
|
|
Interior/Exterior Lathing
|
5/25/2022
|
Corrections Issued
|
BRENDAN LOONEY
|
|
Drywall Nailing
|
5/27/2022
|
Approved
|
BRENDAN LOONEY
|
|
Special/Order Compliance
|
5/27/2022
|
Approved
|
BRENDAN LOONEY
|
|
HVAC-Final
|
8/11/2023
|
Partial Approval
|
STEPHANIE SWANSON
|
|
BUILDING-Rough-Frame
|
10/4/2023
|
Approved
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Final
|
10/4/2023
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
PLUMBING-Final
|
10/4/2023
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
ELECTRICAL-Final
|
10/11/2023
|
Approved
|
STEPHANIE SWANSON
|
|
Final
|
10/11/2023
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Gas Test
|
10/11/2023
|
Approved
|
STEPHANIE SWANSON
|
|
HVAC-Final
|
10/11/2023
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
PLUMBING-Final
|
10/11/2023
|
Approved
|
STEPHANIE SWANSON
|
|
SGSOV-Seismic Gas S/O Valve
|
10/11/2023
|
SGSOV Approved
|
STEPHANIE SWANSON
|
|
Smoke Detectors
|
10/11/2023
|
Approved
|
STEPHANIE SWANSON
|
|
HVAC-Final
|
10/16/2023
|
Approved
|
STEPHANIE SWANSON
|
|
Footing/Foundation/Slab
|
2/6/2024
|
Approved
|
STEPHANIE SWANSON
|
|
Reinforced Concrete Frame
|
2/6/2024
|
Approved
|
STEPHANIE SWANSON
|
|
Final
|
10/10/2024
|
OK to Issue CofO
|
STEPHANIE SWANSON
|
|
Green Building Final
|
10/10/2024
|
Approved
|
STEPHANIE SWANSON
|