1245 W 16TH ST 90731
Certificate Information: 1245 W 16TH ST 90731
- Application / Permit
- 19014-30000-07134
- Plan Check / Job No.
- B19WL07317
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2-STORY ACCESSORY DWELLING UNIT ADDITION TO (E) 1-STORY 1-CAR GARAGE.
- Permit Issued
- Issued on 8/11/2021
- Issuing Office
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Green Plans Picked Up | 2/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | SERGIO SILVA |
| Corrections Issued | 2/18/2020 | SERGIO SILVA |
| Quality Review Completed | 2/27/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/28/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 12/28/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 1/14/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 2/8/2021 | SERGIO SILVA |
| Plan Check Approved | 7/15/2021 | SERGIO SILVA |
| Issued | 8/11/2021 | APPLICANT |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| CofO in Progress | 12/22/2023 | JAMES CHAVEZ |
| Permit Finaled | 12/27/2023 | ANSON MAGLASANG |
| CofO Issued | 12/27/2023 | ANSON MAGLASANG |
| Permit Finaled | 12/27/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Green Code | Cleared | 2/27/2020 | DONALD CRICHLOW |
| Address approval | Cleared | 9/30/2020 | CHINH DINH |
| Permit | Cleared | 9/30/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2020 | CHINH DINH |
| Sewer availability | Cleared | 10/1/2020 | CHINH DINH |
| Construction within easement | Cleared | 10/2/2020 | WALTER RAMIREZ |
| Construction near power lines | Cleared | 10/3/2020 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 2/8/2021 | SERGIO SILVA |
| Hydrant and Access approval | Cleared | 2/8/2021 | JEREMY CARTER |
| Trees in Parkway | Cleared | 3/31/2021 | JOHN KIM |
| Low Impact Development | Cleared | 7/1/2021 | MARTIN FRAGOSO |
| GPI Written Notices | Cleared | 7/15/2021 | SERGIO SILVA |
| Roof/Waste drainage to street | Cleared | 7/22/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/10/2022 | Partial Inspection | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 2/14/2022 | Partial Inspection | ANSON MAGLASANG |
| Pre-Inspection | 2/14/2022 | Partial Inspection | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 2/23/2022 | Approved | ANSON MAGLASANG |
| Footing/Foundation/Slab | 2/23/2022 | Approved | ANSON MAGLASANG |
| Sewer | 2/23/2022 | Approved | ANSON MAGLASANG |
| Wood Frame | 3/3/2022 | Partial Approval | ANSON MAGLASANG |
| Service/Power Release | 3/17/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2022 | Partial Approval | ANSON MAGLASANG |
| Wood Frame | 5/10/2022 | Partial Approval | ANSON MAGLASANG |
| Rough-Elec/Plmb/HVAC | 6/14/2022 | Partial Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 6/22/2022 | Approved | ANSON MAGLASANG |
| Shower Pan | 6/22/2022 | Approved | ANSON MAGLASANG |
| Insulation | 6/27/2022 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/12/2022 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 7/19/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Interior/Exterior Lathing | 7/19/2022 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 7/28/2022 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 7/28/2022 | Approved | ANSON MAGLASANG |
| Green Building Rough | 7/28/2022 | Approved | ANSON MAGLASANG |
| Insulation | 7/28/2022 | Approved | ANSON MAGLASANG |
| HVAC-Rough | 8/15/2022 | Approved | ANSON MAGLASANG |
| Interior/Exterior Lathing | 11/15/2022 | Partial Approval | ANSON MAGLASANG |
| HVAC-Final | 1/11/2023 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 1/12/2023 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 7/12/2023 | Corrections Issued | JAMES CHAVEZ |
| Service/Power Release | 7/19/2023 | Approved | JAMES CHAVEZ |
| Gas Test | 9/6/2023 | Approved | ANSON MAGLASANG |
| Special/Order Compliance | 9/6/2023 | Partial Inspection | ANSON MAGLASANG |
| ELECTRICAL-Final | 11/7/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Final | 11/7/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Final | 11/7/2023 | Corrections Issued | JAMES CHAVEZ |
| Smoke Detectors | 11/7/2023 | Corrections Issued | JAMES CHAVEZ |
| Special/Order Compliance | 11/13/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 11/20/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 11/20/2023 | Approved | JAMES CHAVEZ |
| Final | 12/21/2023 | OK to Issue CofO | JAMES CHAVEZ |
| Green Building Final | 12/21/2023 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 12/21/2023 | SGSOV Approved | JAMES CHAVEZ |
| Smoke Detectors | 12/21/2023 | Approved | JAMES CHAVEZ |
| Service/Power Release | 12/22/2023 | Approved | JAMES CHAVEZ |