12951 W PANAMA ST 90066
Certificate Information: 12951 W PANAMA ST 90066
- Application / Permit
- 19014-30000-07055
- Plan Check / Job No.
- B19WL07258
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND RENOVATION TO (E) 1-STORY TYPE VB SINGLE FAMILY DWELLING. ADDITION OF 11SF THE INCORPORATION OF (N) BATH, RENOVATED KITCHEN, RELOCATION OF LAUNDY AND REDESIGN/REFRAME ROOF. BUILDING TO BE EQUIPPED WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 9/25/2020
- Issuing Office
- Current Status
- CofO Issued on 7/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | SERGIO SILVA |
| Corrections Issued | 1/30/2020 | SERGIO SILVA |
| Quality Review Completed | 2/6/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/16/2020 | SERGIO SILVA |
| Green Plans Picked Up | 7/30/2020 | APPLICANT |
| Plan Check Approved | 8/25/2020 | SERGIO SILVA |
| Building Plans Picked Up | 8/31/2020 | APPLICANT |
| Issued | 9/25/2020 | APPLICANT |
| CofO in Progress | 7/26/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 7/30/2024 | DANIEL ORRANTE |
| CofO Issued | 7/30/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/30/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/5/2020 | JOHN CONNEALLY |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2020 | DINAH GARIN |
| Green Code | Cleared | 7/30/2020 | RICHARD GARCIA |
| Low Impact Development | Cleared | 8/5/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 8/14/2020 | DINAH GARIN |
Contact Information
| Architect | Gelfat,, James Evan; Lic. No.: C19847 | 10748 FLAXTON ST CULVER CITY, CA 90230 |
| Contractor | Luxus Construction Inc; Lic. No.: 964722-B | 15332 ANTIOCH ST #109 PACIFIC PALISADES, CA 90272 |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/13/2020 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/13/2020 | Partial Approval | JOHNNY MIRANDA |
| METHANE-Barrier | 10/13/2020 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 10/13/2020 | Approved | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 12/7/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2020 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 12/29/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 12/29/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 12/29/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 12/29/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/29/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 12/31/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 12/31/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 12/31/2020 | Approved | JOHNNY MIRANDA |
| MERV13>=Rough | 12/31/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/31/2020 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/19/2021 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 2/5/2021 | Partial Approval | DAVID HEINE |
| Green Building Rough | 2/5/2021 | Not Ready for Inspection | DAVID HEINE |
| MERV13>=Rough | 2/5/2021 | Not Ready for Inspection | DAVID HEINE |
| PLUMBING-Rough | 2/5/2021 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 3/18/2021 | Partial Approval | DAVID HEINE |
| Deputy Wood Construction | 3/18/2021 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 3/18/2021 | Approved | DAVID HEINE |
| Green Building Rough | 3/18/2021 | Not Ready for Inspection | DAVID HEINE |
| MERV13>=Rough | 3/18/2021 | Not Ready for Inspection | DAVID HEINE |
| Interior/Exterior Lathing | 4/23/2021 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 5/14/2021 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 5/17/2021 | Approved | PIERRE VEGA |
| Green Building Rough | 5/17/2021 | Approved | PIERRE VEGA |
| Insulation | 5/17/2021 | Approved | PIERRE VEGA |
| MERV13>=Rough | 5/17/2021 | Approved | PIERRE VEGA |
| PLUMBING-Rough | 5/17/2021 | Approved | PIERRE VEGA |
| Shower Pan | 5/17/2021 | Approved | PIERRE VEGA |
| Drywall Nailing | 6/1/2021 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 6/28/2021 | Approved | AMY COLIN |
| Final | 2/13/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 2/13/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Green Building Final | 2/13/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| MERV13>=Final | 2/13/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 2/13/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 2/22/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/22/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 2/22/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/22/2024 | Approved | TEMISTOCLES CAAL |
| Final | 7/25/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 7/25/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 7/25/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 7/25/2024 | Approved | TEMISTOCLES CAAL |