4212 S ALLA ROAD 90066

Certificate Information: 4212 S ALLA ROAD 90066

Application / Permit
19014-30000-07023
Plan Check / Job No.
B19WL07226
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF 26'-1 1/2" X 23'-1/2" (556 SF) 2ND FLOOR ADU OVER (E) DETACHED 2-CAR GARAGE & STORAGE ROOM. ADD ROOF DECK ON TOP OF ADU.
Permit Issued
Issued on 12/15/2020
Issuing Office
Current Status
CofO Issued on 10/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 CHUNG-WEN CHUANG
Corrections Issued 3/5/2020 CHUNG-WEN CHUANG
Quality Review Completed 3/25/2020 KESETE HAREGOT
Building Plans Picked Up 3/31/2020 APPLICANT
Green Plans Picked Up 8/26/2020 APPLICANT
Applicant returned to address corrections 9/14/2020 CHUNG-WEN CHUANG
Applicant returned to address corrections 10/22/2020 CHUNG-WEN CHUANG
Applicant returned to address corrections 10/28/2020 CHUNG-WEN CHUANG
Plan Check Approved 11/23/2020 CHUNG-WEN CHUANG
Issued 12/15/2020 APPLICANT
CofO in Progress 10/25/2023 RICHARD STEINBACH
Permit Finaled 10/28/2023 DANIEL ORRANTE
CofO Issued 10/28/2023 DANIEL ORRANTE
Permit Finaled 10/28/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/24/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 6/24/2020 ANTHONY MAINEZ
Sewer availability Cleared 7/9/2020 ANTHONY MAINEZ
Specific Plan Cleared 7/9/2020 PEDRO AYALA
Miscellaneous Cleared 8/26/2020 ANTHONY MAINEZ
Green Code Cleared 9/4/2020 DONALD CRICHLOW
Low Impact Development Cleared 10/6/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/17/2020 ANTHONY MAINEZ

Contact Information

Architect Howell,, Ronald Edwards; Lic. No.: C21122 P O BOX 661007      LOS ANGELES, CA 90066
Contractor Bernal C J Const Co; Lic. No.: 440187-B PO BOX 1161      WHITTIER, CA 90609

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/21/2020 Approved ENRIQUE MIRELES
Deputy Steel/Welding 1/7/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/9/2021 Partial Approval ENRIQUE MIRELES
Green Building Rough 2/9/2021 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 3/24/2021 Approved ENRIQUE MIRELES
Green Building Rough 3/24/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 4/8/2021 Corrections Issued ENRIQUE MIRELES
Pre-Inspection 4/28/2021 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Approved ENRIQUE MIRELES
Deputy Wood Construction 5/7/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 5/12/2021 Approved ENRIQUE MIRELES
Insulation 5/17/2021 Approved PIERRE VEGA
Drywall Nailing 5/20/2021 Conditional Approval RYAN SALAZAR
Interior/Exterior Lathing 6/23/2021 Approved ENRIQUE MIRELES
Drywall Nailing 3/3/2022 Approved ENRIQUE MIRELES
Final 3/3/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 3/3/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 3/3/2022 Approved ENRIQUE MIRELES
Final 5/25/2022 Corrections Issued PATRICK QUALEY
Gas Test 5/25/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 6/6/2022 Not Ready for Inspection JESUS RODRIGUEZ
Final 6/8/2022 Not Ready for Inspection PATRICK QUALEY
Smoke Detectors 6/9/2022 Approved PATRICK QUALEY
Final 10/3/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 10/13/2022 Corrections Issued JESUS RODRIGUEZ
Final 10/13/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 10/13/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 10/13/2022 Approved JESUS RODRIGUEZ
Pre-Inspection 4/11/2023 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 7/31/2023 Approved JESUS RODRIGUEZ
HVAC-Final 7/31/2023 Approved JESUS RODRIGUEZ
Final 10/24/2023 OK to Issue CofO JESUS RODRIGUEZ