1455 S CARDIFF AVE 90035

Certificate Information: 1455 S CARDIFF AVE 90035

Application / Permit
19014-30000-07017
Plan Check / Job No.
B19WL07220
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND FLOOR ADDITION TO (E) 1-STORY SFD TO ADD A NEW BEDROOM & BATHROOM. (665 SF)
Permit Issued
Issued on 4/5/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 REZA HAGHIGHAT
Green Plans Picked Up 1/16/2020 APPLICANT
Corrections Issued 1/21/2020 REZA HAGHIGHAT
Quality Review Completed 1/30/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/1/2021 APPLICANT
Plan Check Approved 3/18/2021 REZA HAGHIGHAT
Issued 4/5/2021 APPLICANT
CofO in Progress 9/21/2022 KENNETH NAGLE
Permit Finaled 9/23/2022 DANIEL ORRANTE
CofO Issued 9/23/2022 DANIEL ORRANTE
Permit Finaled 9/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/3/2020 CATHERINE ADROVER
Grading Pre-Inspection Cleared 9/8/2020 BARTON HOLMES
Miscellaneous Cleared 9/11/2020 NIKTA MOUSAVI
Sewer availability Cleared 9/14/2020 CATHERINE ADROVER
Green Code Cleared 11/22/2020 RICHARD GARCIA
Low Impact Development Cleared 3/4/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 3/12/2021 DINAH GARIN

Contact Information

Architect Mac, Gillivray, Troyer Scott; Lic. No.: C9504 11907 W PICO BLVD      LOS ANGELES, CA 90064
Contractor Owner-Builder       ,
Engineer Guzman,, Martin; Lic. No.: C79193 4054 W 165TH STREET      LAWNDALE, CA 90260

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/8/2021 No Result Entered RONALD WEBER
Excavation/Setback/Form/Re-Bar 6/8/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 6/8/2021 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 6/8/2021 Approved KEVIN SARGSYAN
METHANE-Subgrade 6/8/2021 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 6/28/2021 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 6/29/2021 Approved DONALD GALLAGHER
Deputy Reinf. Concrete 7/26/2021 Conditional Approval KEVIN SARGSYAN
Deputy Steel/Welding 7/28/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 7/28/2021 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 7/28/2021 Approved KEVIN SARGSYAN
Underground Mechanical 7/28/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 8/6/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 8/9/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/24/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/26/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/7/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 10/20/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 10/20/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 10/20/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 10/28/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 11/2/2021 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 11/22/2021 Approved KEVIN SARGSYAN
Green Building Rough 11/22/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 11/22/2021 Partial Approval KEVIN SARGSYAN
METHANE-Rough 11/22/2021 Approved KEVIN SARGSYAN
Insulation 12/1/2021 Approved KEVIN SARGSYAN
Shower Pan 12/1/2021 Approved KEVIN SARGSYAN
Drywall Nailing 12/8/2021 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 12/8/2021 Approved STEPHANIE SWANSON
Final 2/23/2022 Corrections Issued EVAN COOPER
Green Building Final 2/23/2022 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/23/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 2/23/2022 Approved EVAN COOPER
Structural Steel Frame 2/23/2022 Approved EVAN COOPER
Final 9/21/2022 OK to Issue CofO KENNETH NAGLE