2358 N GLOVER PL 90031

Certificate Information: 2358 N GLOVER PL 90031

Application / Permit
19014-30000-07010
Plan Check / Job No.
B19WL07216
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and interior remodel of (E) SFD. Additon to (E) detached 1- car garage and attach to the (E) SFD. Resulting garage addition to include storage and 1 car garage. Per engineering design.
Permit Issued
Issued on 1/29/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 12/23/2019 JAHANSHAH POURHASSAN
Corrections Issued 1/9/2020 JAHANSHAH POURHASSAN
Building Plans Picked Up 1/14/2020 APPLICANT
Plan Check Approved 1/28/2020 ALFREDO JARA
Issued 1/29/2020 LADBS
CofO in Progress 9/30/2020 ROBERT VORHIS
Permit Finaled 12/31/2020 DEROLD HAUFF
CofO Issued 12/31/2020 DEROLD HAUFF
Permit Finaled 12/31/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/15/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 1/15/2020 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/3/2020 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/13/2020 Corrections Issued HORACE FULTZ
Excavation/Setback/Form/Re-Bar 2/19/2020 Not Ready for Inspection AJA COLLAY
Excavation/Setback/Form/Re-Bar 2/20/2020 Conditional Approval AJA COLLAY
BUILDING-Rough-Frame 5/11/2020 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 5/11/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 5/11/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 5/11/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 5/11/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 5/14/2020 Partial Inspection RUBEN SALAS
BUILDING-Rough-Frame 5/19/2020 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 5/19/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 5/19/2020 Approved KATHRYN BUTTERWORTH
HVAC-Rough 5/19/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 5/19/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 5/22/2020 Not Ready for Inspection ROBERT VORHIS
Interior/Exterior Lathing 5/27/2020 Approved THOMAS LOGRASSO
Insulation 6/2/2020 Approved THOMAS LOGRASSO
Drywall Nailing 6/8/2020 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 6/8/2020 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 6/8/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 6/11/2020 Approved THOMAS LOGRASSO
Drywall Nailing 8/10/2020 Approved ROBERT VORHIS
Final 8/10/2020 Not Ready for Inspection ROBERT VORHIS
Green Building Final 8/10/2020 Partial Inspection ROBERT VORHIS
PLUMBING-Final 8/10/2020 Approved ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 8/10/2020 SGSOV Not Ready ROBERT VORHIS
Smoke Detectors 8/10/2020 Approved ROBERT VORHIS
Final 8/18/2020 Corrections Issued JOSEPH MCGARRY
Service/Power Release 8/18/2020 Not Required JOSEPH MCGARRY
Final 9/1/2020 Conditional Approval ROBERT VORHIS
Footing/Foundation/Slab 9/1/2020 Approved ROBERT VORHIS
Green Building Final 9/1/2020 Approved ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 9/1/2020 SGSOV Approved ROBERT VORHIS