1415 S CRESTVIEW CT 90024
Certificate Information: 1415 S CRESTVIEW CT 90024
- Application / Permit
- 19014-30000-06992
- Plan Check / Job No.
- B19WL07188
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and alteration to (E) single family dwelling.NFPA-13D fully sprinklered thru-out.
- Permit Issued
- Issued on 7/24/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | ALFREDO JARA |
| Corrections Issued | 2/3/2020 | ALFREDO JARA |
| Green Plans Picked Up | 2/5/2020 | APPLICANT |
| Quality Review Completed | 2/14/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/13/2020 | ALFREDO JARA |
| Plan Check Approved | 7/21/2020 | ALFREDO JARA |
| Building Plans Picked Up | 7/21/2020 | APPLICANT |
| Issued | 7/24/2020 | APPLICANT |
| CofO in Progress | 5/20/2024 | STEPHANIE SWANSON |
| Permit Finaled | 6/5/2024 | DANIEL ORRANTE |
| CofO Issued | 6/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/21/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 5/1/2020 | RICHARD GARCIA |
| Low Impact Development | Cleared | 6/30/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 7/16/2020 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 7/17/2020 | WALTER RAMIREZ |
| GPI Written Notices | Cleared | 7/21/2020 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 7/21/2020 | ALFREDO JARA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khazra,, Afshin; Lic. No.: C50250 | 22855 PAUL REVERE DR CALABASAS, CA 91302 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/25/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 3/2/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Barrier | 3/2/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 3/2/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 3/5/2021 | Partial Approval | ANTHONY MCDOWALL |
| Sewer | 3/5/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 3/9/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2021 | Partial Approval | ANTHONY MCDOWALL |
| PLUMBING-Rough | 6/3/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 6/8/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 6/24/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 7/7/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 7/7/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 7/13/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 7/13/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 8/3/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/3/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/3/2021 | Partial Approval | ALIZAH MAYAGOITIA |
| Shower Pan | 8/3/2021 | Approved | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 8/3/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 8/3/2021 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/16/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 8/16/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 8/16/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 8/16/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 8/25/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 9/14/2021 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 2/13/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 2/27/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Deputy Wood Construction | 10/10/2023 | Conditional Approval | STEPHANIE SWANSON |
| ELECTRICAL-Final | 11/17/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Final | 11/28/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 11/28/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Service/Power Release | 11/28/2023 | Approved | STEPHANIE SWANSON |
| Final | 1/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 1/18/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 1/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 1/18/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 1/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 1/31/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Final | 1/31/2024 | Approved | STEPHANIE SWANSON |
| Smoke Detectors | 1/31/2024 | Approved | STEPHANIE SWANSON |
| Final | 5/20/2024 | OK to Issue CofO | STEPHANIE SWANSON |