530 S LORING AVE 90024
Certificate Information: 530 S LORING AVE 90024
- Application / Permit
- 19014-30000-06981
- Plan Check / Job No.
- B19WL07169
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition to and existing 2-story SFD
- Permit Issued
- Issued on 7/14/2020
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 7/14/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | KAVIAN REFAHI |
| Corrections Issued | 1/29/2020 | KAVIAN REFAHI |
| Quality Review Completed | 2/7/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/4/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 6/4/2020 | KAVIAN REFAHI |
| Green Plans Picked Up | 6/16/2020 | APPLICANT |
| Applicant returned to address corrections | 6/29/2020 | KAVIAN REFAHI |
| Plan Check Approved | 7/6/2020 | KAVIAN REFAHI |
| Issued | 7/14/2020 | APPLICANT |
| Building Plans Picked Up | 7/15/2020 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/13/2020 | AL GAMBLE |
| CPC | Cleared | 5/29/2020 | LOUIS ORTEGA |
| Green Code | Cleared | 6/12/2020 | RICHARD GARCIA |
| Low Impact Development | Cleared | 6/16/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 6/19/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2020 | DINAH GARIN |
| Sewer availability | Cleared | 6/23/2020 | DINAH GARIN |
| GPI Written Notices | Cleared | 7/6/2020 | KAVIAN REFAHI |
Contact Information
| Contractor | United Remodeling Construction Inc; Lic. No.: 813590-B | 4924 BALBOA BLVD #447 ENCINO, CA 91316 |
| Engineer | Enayat,, Simhaee; Lic. No.: C37206 | 1332 S ST JOSEPH PL LOS ANGELES, CA 90015 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/18/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 8/18/2020 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 11/25/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 12/1/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 12/9/2020 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 12/23/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 12/23/2020 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 12/23/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 4/21/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 4/21/2021 | Approved | ANTHONY MCDOWALL |
| Green Building Rough | 4/21/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 4/21/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 4/21/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 4/23/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 4/26/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 4/26/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 4/26/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 6/7/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 6/7/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 6/7/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/7/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 6/17/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 6/17/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 6/17/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 6/17/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 6/21/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 6/21/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 6/28/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 6/28/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 12/15/2021 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Final | 1/14/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 1/26/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 2/2/2022 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Final | 2/3/2022 | Partial Approval | BRENDAN LOONEY |
| Special/Order Compliance | 2/3/2022 | Corrections Issued | BRENDAN LOONEY |
| Gas Test | 3/17/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 3/17/2022 | SGSOV Not Ready | BRENDAN LOONEY |
| Special/Order Compliance | 3/17/2022 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 3/18/2022 | Partial Approval | BRENDAN LOONEY |
| Pre-Inspection | 3/21/2022 | Partial Inspection | BRENDAN LOONEY |
| ELECTRICAL-Final | 4/4/2022 | Approved | BRENDAN LOONEY |
| Final | 4/4/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 4/4/2022 | Approved | BRENDAN LOONEY |