12683 W PALMS BLVD 90066
Certificate Information: 12683 W PALMS BLVD 90066
- Application / Permit
- 19014-30000-06958
- Plan Check / Job No.
- B19WL07147
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2-story accessory dwelling unit addition, per ab229 and sb494, to (e) detached 1-story 2-car garage w/spiral staircase.
- Permit Issued
- Issued on 5/13/2020
- Issuing Office
- Current Status
- CofO Issued on 2/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2020 | MANUEL GARCIA |
| Corrections Issued | 1/29/2020 | MANUEL GARCIA |
| Green Plans Picked Up | 2/5/2020 | APPLICANT |
| Quality Review Completed | 2/6/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 2/6/2020 | APPLICANT |
| Applicant returned to address corrections | 3/2/2020 | MANUEL GARCIA |
| Plan Check Approved | 3/3/2020 | MANUEL GARCIA |
| Issued | 5/13/2020 | APPLICANT |
| CofO in Progress | 2/1/2021 | ENRIQUE MIRELES |
| Permit Finaled | 2/11/2021 | VINCENT COTTON |
| CofO Issued | 2/11/2021 | VINCENT COTTON |
| Permit Finaled | 2/11/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2020 | NIKTA MOUSAVI |
| Construction near power lines | Cleared | 3/2/2020 | OSCAR CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2020 | NIKTA MOUSAVI |
| GPI Written Notices | Cleared | 3/2/2020 | MANUEL GARCIA |
| Grading Pre-Inspection | Cleared | 3/2/2020 | MANUEL GARCIA |
| Roof/Waste drainage to street | Cleared | 3/2/2020 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 3/2/2020 | NIKTA MOUSAVI |
| Green Code | Cleared | 3/3/2020 | RICHARD GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 5525 CANOGA AVE APT 208 WOODLAND HILLS, CA 91367 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/15/2020 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 5/15/2020 | Partial Inspection | DAVID FEILER |
| Deputy Drilled-In Anchors | 5/20/2020 | Approved | DAVID FEILER |
| PLUMBING-Rough | 5/20/2020 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 5/26/2020 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 5/28/2020 | Partial Approval | DAVID FEILER |
| Deputy Drilled-In Anchors | 6/4/2020 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 6/4/2020 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2020 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 7/10/2020 | Corrections Issued | ANTHONY MCDOWALL |
| PLUMBING-Rough | 7/20/2020 | Approved | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 8/31/2020 | Conditional Approval | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 8/31/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Green Building Rough | 8/31/2020 | Corrections Issued | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 9/4/2020 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/4/2020 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/4/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/17/2020 | Approved | CRAIG DAVIS |
| Insulation | 9/23/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 9/29/2020 | Approved | PIERRE VEGA |
| HVAC-Final | 12/9/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Final | 12/14/2020 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 12/14/2020 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 12/14/2020 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/16/2020 | Approved | ENRIQUE MIRELES |
| Final | 12/16/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/16/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/16/2020 | SGSOV Approved | ENRIQUE MIRELES |
| Final | 2/1/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 2/1/2021 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/1/2021 | Approved | ENRIQUE MIRELES |