2907 S RIMPAU BLVD 90016

Certificate Information: 2907 S RIMPAU BLVD 90016

Application / Permit
19014-30000-06929
Plan Check / Job No.
B19WL07124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDITION/REMODEL TO (E) 1-STORY SFD
Permit Issued
Issued on 3/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 TARIK SAOUD
Corrections Issued 1/13/2020 TARIK SAOUD
Green Plans Picked Up 1/14/2020 APPLICANT
Quality Review Completed 1/22/2020 FELIX FIGUEROA
Plan Check Approved 3/5/2020 TARIK SAOUD
Issued 3/12/2020 LADBS
Building Plans Picked Up 9/24/2020 APPLICANT
CofO in Progress 9/30/2024 JUSTIN HAWLEY
CofO Issued 10/3/2024 RUBEN SALAS
Permit Finaled 10/3/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/12/2020 NIKTA MOUSAVI
Sewer availability Cleared 2/12/2020 NIKTA MOUSAVI
Green Code Cleared 2/25/2020 RICHARD GARCIA
Low Impact Development Cleared 3/4/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/4/2020 JAMES MORALEZ
Hold Cleared 4/17/2020 JEREMY CORONEL

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/29/2020 Conditional Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 6/26/2020 Conditional Approval MATTHEW NUCKOLLS
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Approved MATTHEW NUCKOLLS
Footing/Foundation/Slab 6/26/2020 Not Ready for Inspection MATTHEW NUCKOLLS
Insulation 6/26/2020 Not Ready for Inspection MATTHEW NUCKOLLS
PLUMBING-Rough 6/26/2020 Corrections Issued MATTHEW NUCKOLLS
Reinforced Masonry Frame 6/26/2020 Not Ready for Inspection MATTHEW NUCKOLLS
Wood Frame 6/26/2020 Not Ready for Inspection MATTHEW NUCKOLLS
ELECTRICAL-Rough 7/8/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 7/8/2020 Approved STUART CHAPMAN
PLUMBING-Rough 7/8/2020 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 7/24/2020 Approved STUART CHAPMAN
Wood Frame 7/24/2020 Corrections Issued STUART CHAPMAN
Deputy Wood Construction 7/31/2020 No Access for Inspection ELMER BLAND
HVAC-Rough 8/6/2020 Approved STUART CHAPMAN
Wood Frame 8/6/2020 Partial Approval STUART CHAPMAN
Insulation 8/12/2020 Approved CRAIG VAUGHAN
Wood Frame 8/12/2020 Partial Approval CRAIG VAUGHAN
Drywall Nailing 8/17/2020 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 10/26/2020 Approved STUART CHAPMAN
Final 10/26/2020 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 10/26/2020 Approved STUART CHAPMAN
Green Building Final 10/26/2020 Approved STUART CHAPMAN
Green Building Rough 10/26/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/26/2020 SGSOV Approved STUART CHAPMAN
Smoke Detectors 10/26/2020 Approved STUART CHAPMAN
Final 12/2/2020 Not Ready for Inspection STUART CHAPMAN
Final 12/8/2020 Conditional Approval STUART CHAPMAN
Final 5/10/2021 Not Ready for Inspection STUART CHAPMAN
Final 2/17/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 9/30/2024 Approved JUSTIN HAWLEY
Final 9/30/2024 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 9/30/2024 Approved JUSTIN HAWLEY
PLUMBING-Final 9/30/2024 Approved JUSTIN HAWLEY