1028 N VILLA GROVE DR 90272

Certificate Information: 1028 N VILLA GROVE DR 90272

Application / Permit
19014-30000-06901
Plan Check / Job No.
B19WL07107
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st & 2nd floor addition to (e) 1-story SFD.
Permit Issued
Issued on 11/24/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Assigned to Plan Check Engineer 1/6/2020 REZA HAGHIGHAT
Corrections Issued 1/22/2020 REZA HAGHIGHAT
Quality Review Completed 1/30/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 8/31/2020 APPLICANT
Plan Check Approved 10/5/2020 REZA HAGHIGHAT
Issued 11/24/2020 APPLICANT
Building Plans Picked Up 11/24/2020 APPLICANT
CofO in Progress 12/1/2021 JOHN KIDWELL
Permit Finaled 2/14/2022 DANIEL ORRANTE
Permit Finaled 2/14/2022 DANIEL ORRANTE
CofO Issued 2/14/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 8/14/2020 ORVAL HERNANDEZ-MARCI
BHO/Hillside ordinance Cleared 8/21/2020 MAHELET GEBEYHU
BHO/Hillside ordinance Cleared 8/21/2020 MAHELET GEBEYHU
Roof/Waste drainage to street Cleared 8/21/2020 MAHELET GEBEYHU
Eng Process Fee Ord 176,300 Cleared 8/25/2020 MAHELET GEBEYHU
Sewer availability Cleared 8/25/2020 MAHELET GEBEYHU
Green Code Cleared 8/28/2020 RICHARD GARCIA
BHO/Hillside ordinance Cleared 9/15/2020 RAYMOND MUGAMBWA
GPI Written Notices Cleared 10/5/2020 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 10/5/2020 REZA HAGHIGHAT

Contact Information

Contractor Pacific Design Build Llc; Lic. No.: 1067229-B 4640 ADMIRALTY WAY STE 500      MARINA DEL REY, CA 90292
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 7/19/2021 Approved PIERRE VEGA
Green Building Rough 7/19/2021 Approved PIERRE VEGA
Pre-Inspection 10/4/2021 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 10/22/2021 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 10/22/2021 Not Ready for Inspection JUAN VALENZUELA
Final 10/22/2021 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 10/22/2021 Not Ready for Inspection JUAN VALENZUELA
Green Building Final 10/22/2021 Not Ready for Inspection JUAN VALENZUELA
HVAC-Final 10/22/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 10/22/2021 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 10/22/2021 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 10/22/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 11/30/2021 Approved JOHN KIDWELL
ELECTRICAL-Final 11/30/2021 Approved JOHN KIDWELL
Final 11/30/2021 OK to Issue CofO JOHN KIDWELL
Footing/Foundation/Slab 11/30/2021 Approved JOHN KIDWELL
Green Building Final 11/30/2021 Approved JOHN KIDWELL
HVAC-Final 11/30/2021 Approved JOHN KIDWELL
PLUMBING-Final 11/30/2021 Approved JOHN KIDWELL
Smoke Detectors 11/30/2021 Approved JOHN KIDWELL