7761 W SELMA AVE 90046

Certificate Information: 7761 W SELMA AVE 90046

Application / Permit
19014-30000-06893
Plan Check / Job No.
B19WL07101
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached garage to ADU per AB 494 & SB 229 and convert a separate (E) detached carport to a garage with an addition to connect the (E) garage and caport together.
Permit Issued
Issued on 3/4/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 JAHANSHAH POURHASSAN
Corrections Issued 1/14/2020 JAHANSHAH POURHASSAN
Quality Review Completed 1/24/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 1/27/2020 APPLICANT
Applicant returned to address corrections 2/28/2020 JAHANSHAH POURHASSAN
Plan Check Approved 3/4/2020 JAHANSHAH POURHASSAN
Issued 3/4/2020 LADBS
Building Plans Picked Up 11/12/2020 APPLICANT
CofO in Progress 7/7/2021 JOSEPH MCGARRY
CofO Issued 7/28/2021 DEROLD HAUFF
Permit Finaled 7/28/2021 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 2/18/2020 AMANDA KAINER
Address approval Cleared 2/19/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/19/2020 CELINA MORENO
Hydrant and Access approval Cleared 2/19/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 2/19/2020 CELINA MORENO
Sewer availability Cleared 2/19/2020 CELINA MORENO
Green Code Cleared 2/27/2020 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/9/2020 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 10/9/2020 Not Ready for Inspection RAUL BARAJAS
Underground Mechanical 10/14/2020 Approved RAUL BARAJAS
Underground Mechanical 10/27/2020 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 11/6/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 11/6/2020 Corrections Issued RAUL BARAJAS
Underground Mechanical 11/6/2020 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 12/17/2020 Partial Approval RAUL BARAJAS
Gas Test 12/17/2020 Approved RAUL BARAJAS
Interior/Exterior Lathing 12/17/2020 Approved RAUL BARAJAS
PLUMBING-Rough 12/17/2020 Partial Approval RAUL BARAJAS
Wood Frame 12/17/2020 Approved RAUL BARAJAS
Insulation 1/7/2021 Approved RAUL BARAJAS
Shower Pan 1/7/2021 Not Ready for Inspection RAUL BARAJAS
Shower Pan 1/13/2021 Approved RAUL BARAJAS
Drywall Nailing 1/22/2021 Approved RAUL BARAJAS
Green Building Rough 1/22/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 1/22/2021 Approved RAUL BARAJAS
Underground Mechanical 2/16/2021 Partial Approval RAUL BARAJAS
Underground Mechanical 3/15/2021 Corrections Issued RAUL BARAJAS
Gas Test 3/23/2021 Approved RAUL BARAJAS
PLUMBING-Rough 3/23/2021 Partial Approval RAUL BARAJAS
Sewer 3/23/2021 Approved RAUL BARAJAS
Underground Mechanical 3/23/2021 Corrections Issued RAUL BARAJAS
Underground Mechanical 3/26/2021 Not Ready for Inspection RAUL BARAJAS
Underground Mechanical 4/8/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 6/14/2021 Approved RAUL BARAJAS
ELECTRICAL-Final 6/14/2021 Not Ready for Inspection RAUL BARAJAS
Final 6/14/2021 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 6/14/2021 Approved RAUL BARAJAS
Green Building Final 6/14/2021 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 6/14/2021 Approved RAUL BARAJAS
PLUMBING-Final 6/14/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/14/2021 SGSOV Not Ready RAUL BARAJAS
Service/Power Release 6/14/2021 Corrections Issued RAUL BARAJAS
Smoke Detectors 6/14/2021 Approved RAUL BARAJAS
Final 6/22/2021 Not Ready for Inspection RICHARD STEINBACH
Green Building Final 6/22/2021 Not Ready for Inspection RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV Not Ready RICHARD STEINBACH
Final 6/30/2021 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 6/30/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 6/30/2021 SGSOV Approved JOSEPH MCGARRY