526 N CARMELINA AVE 90049

Certificate Information: 526 N CARMELINA AVE 90049

Application / Permit
19014-30000-06885
Plan Check / Job No.
B19WL07095
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel & addition to (E) Single family dwelling.
Permit Issued
Issued on 9/29/2021
Issuing Office
Current Status
CofO Issued on 7/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 ALFREDO JARA
Corrections Issued 1/13/2020 ALFREDO JARA
Quality Review Completed 1/24/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/24/2020 APPLICANT
Applicant returned to address corrections 8/17/2021 ALFREDO JARA
Plan Check Approved 9/27/2021 ALFREDO JARA
Issued 9/29/2021 APPLICANT
CofO in Progress 7/7/2023 KEVIN SARGSYAN
Permit Finaled 7/8/2023 DANIEL ORRANTE
CofO Issued 7/8/2023 DANIEL ORRANTE
Permit Finaled 7/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 6/7/2021 LOUIS ORTEGA
ZA Case Cleared 6/7/2021 LOUIS ORTEGA
Grading Pre-Inspection Cleared 6/16/2021 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 6/21/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 6/24/2021 ANTHONY MAINEZ
Sewer availability Cleared 6/24/2021 ANTHONY MAINEZ
Low Impact Development Cleared 7/28/2021 JORGE MEJIA LEMUS
Green Code Cleared 8/13/2021 RICHARD GARCIA
Miscellaneous Cleared 9/7/2021 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Fernandez,, Terry Lynn; Lic. No.: S3256 1719 CARVER ST      REDONDO BEACH, CA 90278

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/23/2021 Partial Approval JUAN VALENZUELA
HVAC-Rough 11/23/2021 Partial Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Partial Approval JUAN VALENZUELA
HVAC-Rough 12/22/2021 Partial Approval JUAN VALENZUELA
Insulation 12/22/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Partial Approval ANDREW NAVE
Wood Frame 1/7/2022 Partial Approval ANDREW NAVE
Deputy Drilled-In Anchors 1/12/2022 Conditional Approval ANDREW NAVE
ELECTRICAL-Rough 1/12/2022 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 1/12/2022 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/12/2022 Partial Inspection JUAN VALENZUELA
Footing/Foundation/Slab 1/12/2022 Partial Approval JUAN VALENZUELA
Drywall Nailing 1/21/2022 Partial Approval JUAN VALENZUELA
Green Building Rough 1/21/2022 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 1/21/2022 Partial Approval JUAN VALENZUELA
Interior/Exterior Lathing 1/21/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 1/21/2022 Partial Inspection JUAN VALENZUELA
Underground Mechanical 1/21/2022 Partial Approval JUAN VALENZUELA
Shower Pan 1/31/2022 Not Ready for Inspection JUAN VALENZUELA
Structural Steel Frame 1/31/2022 Approved JUAN VALENZUELA
Wood Frame 1/31/2022 Not Ready for Inspection JUAN VALENZUELA
Deputy Steel/Welding 2/2/2022 Conditional Approval JUAN VALENZUELA
Shower Pan 2/3/2022 Approved DEANDRE HOFFMAN
Deputy Steel/Welding 2/17/2022 Conditional Approval JUAN VALENZUELA
Drywall Nailing 2/28/2022 Partial Approval JOHN KIDWELL
Green Building Rough 2/28/2022 Partial Approval JOHN KIDWELL
Rough-Elec/Plmb/HVAC 2/28/2022 Partial Approval JOHN KIDWELL
Wood Frame 2/28/2022 Partial Approval JOHN KIDWELL
Drywall Nailing 4/11/2022 Partial Approval JUAN VALENZUELA
Green Building Rough 4/11/2022 Not Ready for Inspection JUAN VALENZUELA
Insulation 4/11/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 4/11/2022 Approved JUAN VALENZUELA
Deputy Steel/Welding 4/19/2022 Approved MICHAEL PELHAM
Deputy Steel/Welding 4/29/2022 Conditional Approval JUAN VALENZUELA
Deputy Steel/Welding 7/14/2022 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 7/27/2022 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 7/27/2022 Partial Approval ANDREW NAVE
Green Building Rough 7/27/2022 Not Ready for Inspection ANDREW NAVE
HVAC-Rough 7/27/2022 Partial Approval ANDREW NAVE
Insulation 7/27/2022 Not Ready for Inspection ANDREW NAVE
Light Gage Steel Frame 7/27/2022 Partial Approval ANDREW NAVE
PLUMBING-Rough 7/27/2022 Partial Approval ANDREW NAVE
Drywall Nailing 8/5/2022 Partial Approval JUAN VALENZUELA
Green Building Rough 8/5/2022 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 8/29/2022 Partial Approval JUAN VALENZUELA
Wood Frame 8/29/2022 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 9/19/2022 Partial Approval JUAN VALENZUELA
Drywall Nailing 9/19/2022 Partial Approval JUAN VALENZUELA
Green Building Rough 9/19/2022 Not Ready for Inspection JUAN VALENZUELA
Wood Frame 9/23/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 10/13/2022 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/16/2023 Approved STEPHANIE SWANSON
Drywall Nailing 6/16/2023 Approved STEPHANIE SWANSON
ELECTRICAL-Final 6/16/2023 Corrections Issued STEPHANIE SWANSON
Final 6/16/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 6/16/2023 Approved STEPHANIE SWANSON
Green Building Final 6/16/2023 Approved STEPHANIE SWANSON
Green Building Rough 6/16/2023 Approved STEPHANIE SWANSON
HVAC-Final 6/16/2023 Partial Approval STEPHANIE SWANSON
PLUMBING-Final 6/16/2023 Partial Approval STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Approved STEPHANIE SWANSON
Smoke Detectors 6/16/2023 Corrections Issued STEPHANIE SWANSON
Final 6/29/2023 Corrections Issued OGANES TARAKHCHYAN
Smoke Detectors 6/29/2023 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 7/6/2023 Approved KEVIN SARGSYAN
Final 7/6/2023 OK to Issue CofO KEVIN SARGSYAN
HVAC-Final 7/6/2023 Approved KEVIN SARGSYAN
PLUMBING-Final 7/6/2023 Approved KEVIN SARGSYAN