7918 S VICKSBURG AVE 90045

Certificate Information: 7918 S VICKSBURG AVE 90045

Application / Permit
19014-30000-06860
Plan Check / Job No.
B19WL07058
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 &2 story addition to (e) single family dwelling, add an att. 2-car garage
Permit Issued
Issued on 9/23/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 REZA HAGHIGHAT
Corrections Issued 1/13/2020 REZA HAGHIGHAT
Quality Review Completed 1/24/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/18/2020 REZA HAGHIGHAT
Green Plans Picked Up 6/22/2020 APPLICANT
Plan Check Approved 6/29/2020 REZA HAGHIGHAT
Plan Check Approved 9/3/2020 REZA HAGHIGHAT
Issued 9/23/2020 APPLICANT
Building Plans Picked Up 10/7/2020 APPLICANT
CofO in Progress 12/10/2021 ENRIQUE MIRELES
CofO in Progress 12/10/2021 ENRIQUE MIRELES
Permit Finaled 12/15/2021 DANIEL ORRANTE
CofO Issued 12/15/2021 DANIEL ORRANTE
Permit Finaled 12/15/2021 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/28/2020 CHINH DINH
Permit Cleared 1/28/2020 CHINH DINH
Roof/Waste drainage to street Cleared 1/28/2020 CHINH DINH
Sewer availability Cleared 1/28/2020 CHINH DINH
Trees in Parkway Cleared 1/30/2020 JOHN KIM
Low Impact Development Cleared 6/9/2020 ORVAL HERNANDEZ-MARCIAL
Green Code Cleared 6/19/2020 RICHARD GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/23/2020 Approved JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 10/27/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 10/27/2020 Not Ready for Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 11/6/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 11/6/2020 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 11/6/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 11/10/2020 Partial Approval JUAN VALENZUELA
Underground Mechanical 11/10/2020 Partial Inspection JUAN VALENZUELA
Footing/Foundation/Slab 11/18/2020 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 11/20/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 12/1/2020 Partial Inspection JUAN VALENZUELA
Underground Mechanical 12/1/2020 Partial Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 12/15/2020 Partial Approval JUAN VALENZUELA
HVAC-Rough 2/4/2021 Corrections Issued DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 2/5/2021 Corrections Issued DAVID HEINE
PLUMBING-Rough 2/9/2021 Approved DAVID HEINE
ELECTRICAL-Rough 2/11/2021 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Partial Approval DAVID HEINE
Insulation 3/9/2021 Approved DAVID HEINE
Interior/Exterior Lathing 3/9/2021 Partial Approval DAVID HEINE
Drywall Nailing 4/27/2021 Approved BRENDAN LOONEY
Green Building Rough 4/27/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 5/6/2021 Approved BRENDAN LOONEY
ELECTRICAL-Final 7/22/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Final 7/22/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 7/22/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 8/6/2021 Corrections Issued BRENDAN LOONEY
PLUMBING-Final 8/6/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 8/17/2021 Not Ready for Inspection BRENDAN LOONEY
Gas Test 8/17/2021 Approved BRENDAN LOONEY
PLUMBING-Final 8/17/2021 Corrections Issued BRENDAN LOONEY
Service/Power Release 8/17/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 8/31/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 11/5/2021 Approved ENRIQUE MIRELES
Final 11/5/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 11/5/2021 Approved ENRIQUE MIRELES
Green Building Final 11/5/2021 Approved ENRIQUE MIRELES
HVAC-Final 11/5/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/5/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 11/5/2021 Approved ENRIQUE MIRELES
Final 11/24/2021 Not Ready for Inspection BOBBY KEY
Final 12/10/2021 OK to Issue CofO ENRIQUE MIRELES