10832 W LAWLER ST 90034

Certificate Information: 10832 W LAWLER ST 90034

Application / Permit
19014-30000-06858
Plan Check / Job No.
B19WL07055
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel & 2-story addition to (e) SFD and add an att. 2-car garage.
Permit Issued
Issued on 3/2/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2019 APPLICANT
Green Plans Picked Up 1/8/2020 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 REZA HAGHIGHAT
Corrections Issued 1/13/2020 REZA HAGHIGHAT
Quality Review Completed 1/24/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/27/2020 APPLICANT
Plan Check Approved 2/25/2020 REZA HAGHIGHAT
Issued 3/2/2020 LADBS
CofO in Progress 3/26/2021 KENNETH NAGLE
No Progress 3/26/2021 KENNETH NAGLE
CofO in Progress 3/30/2021 KENNETH NAGLE
Permit Finaled 3/30/2021 KENNETH NAGLE
CofO Issued 3/30/2021 KENNETH NAGLE
Permit Finaled 3/30/2021 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/11/2020 JEANETTE VONG
Green Code Cleared 2/11/2020 RICHARD GARCIA
Low Impact Development Cleared 2/11/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 2/11/2020 JEANETTE VONG
Sewer availability Cleared 2/11/2020 JEANETTE VONG
GPI Written Notices Cleared 2/25/2020 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 2/25/2020 REZA HAGHIGHAT

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/26/2020 Conditional Approval KENNETH NAGLE
Footing/Foundation/Slab 5/26/2020 Not Ready for Inspection KENNETH NAGLE
PLUMBING-Rough 5/26/2020 Partial Approval KENNETH NAGLE
Sewer 5/26/2020 Approved KENNETH NAGLE
Footing/Foundation/Slab 5/28/2020 Corrections Issued KENNETH NAGLE
Green Building Rough 6/9/2020 Not Ready for Inspection JUSTIN CURTIS
Footing/Foundation/Slab 7/7/2020 Not Ready for Inspection JUSTIN CURTIS
Excavation/Setback/Form/Re-Bar 7/20/2020 Approved JUSTIN CURTIS
Footing/Foundation/Slab 7/20/2020 Conditional Approval JUSTIN CURTIS
Footing/Foundation/Slab 7/29/2020 No Access for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/31/2020 No Access for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/3/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/14/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Partial Approval EVAN COOPER
Deputy Wood Construction 9/22/2020 Conditional Approval KEVIN SARGSYAN
PLUMBING-Rough 9/28/2020 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 10/6/2020 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 10/6/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 10/22/2020 Approved EVAN COOPER
HVAC-Rough 10/22/2020 Approved EVAN COOPER
Shower Pan 10/22/2020 Approved EVAN COOPER
ELECTRICAL-Rough 10/23/2020 Approved EVAN COOPER
HVAC-Rough 10/23/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 10/26/2020 Approved EVAN COOPER
Green Building Rough 10/26/2020 Approved EVAN COOPER
Insulation 11/4/2020 Approved OGANES TARAKHCHYAN
Sewer 11/4/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 11/13/2020 Approved RICHARD ROBLES
Interior/Exterior Lathing 11/23/2020 Approved RICHARD ROBLES
ELECTRICAL-Final 2/8/2021 Approved OGANES TARAKHCHYAN
Gas Test 2/8/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Final 2/8/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 2/23/2021 Approved RICHARD ROBLES
Service/Power Release 2/23/2021 Approved RICHARD ROBLES
Final 3/12/2021 Conditional Approval KENNETH NAGLE
Footing/Foundation/Slab 3/12/2021 Approved KENNETH NAGLE
Green Building Final 3/12/2021 Approved KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 3/12/2021 SGSOV Approved KENNETH NAGLE
Smoke Detectors 3/12/2021 Approved KENNETH NAGLE