3917 S MCLAUGHLIN AVE 90066
Certificate Information: 3917 S MCLAUGHLIN AVE 90066
- Application / Permit
- 19014-30000-06856
- Plan Check / Job No.
- B19WL07053
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel & 2-story addition to (e) SFD and add an att. 2-car garage.
- Permit Issued
- Issued on 3/2/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Green Plans Picked Up | 1/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | REZA HAGHIGHAT |
| Corrections Issued | 1/13/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 1/24/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 1/27/2020 | APPLICANT |
| Plan Check Approved | 3/2/2020 | REZA HAGHIGHAT |
| Issued | 3/2/2020 | LADBS |
| CofO in Progress | 12/7/2020 | ENRIQUE MIRELES |
| CofO Issued | 1/5/2021 | VINCENT COTTON |
| Permit Finaled | 1/5/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Green Code | Cleared | 2/20/2020 | RICHARD GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | THOMAS LANG |
| Low Impact Development | Cleared | 2/26/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/26/2020 | THOMAS LANG |
| Permit | Cleared | 2/27/2020 | CATHERINE ADROVER |
| Sewer availability | Cleared | 2/27/2020 | CATHERINE ADROVER |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/13/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Underground Mechanical | 5/13/2020 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 5/19/2020 | No Access for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 5/20/2020 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 5/28/2020 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2020 | Corrections Issued | CRAIG DAVIS |
| Deputy Wood Construction | 6/24/2020 | Conditional Approval | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | No Access for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 7/7/2020 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 7/7/2020 | No Access for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/7/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 7/7/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 7/9/2020 | Approved | DAVID HEINE |
| Shower Pan | 7/9/2020 | Approved | DAVID HEINE |
| HVAC-Rough | 7/10/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 7/10/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 7/15/2020 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 7/15/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Wood Frame | 7/17/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 7/23/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 7/23/2020 | Not Ready for Inspection | DAVID HEINE |
| Wood Frame | 7/23/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 7/30/2020 | Not Ready for Inspection | ROBERT SHELLY |
| Green Building Rough | 7/30/2020 | Not Ready for Inspection | ROBERT SHELLY |
| Insulation | 7/30/2020 | Not Ready for Inspection | ROBERT SHELLY |
| Wood Frame | 7/30/2020 | Not Ready for Inspection | ROBERT SHELLY |
| BUILDING-Rough-Frame | 8/4/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Rough | 8/4/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Wood Frame | 8/4/2020 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 8/10/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Rough | 8/10/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Wood Frame | 8/10/2020 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 8/17/2020 | Approved | CRAIG DAVIS |
| Green Building Rough | 8/17/2020 | Approved | CRAIG DAVIS |
| Wood Frame | 8/17/2020 | Approved | CRAIG DAVIS |
| Insulation | 8/18/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 8/18/2020 | Partial Approval | DAVID HEINE |
| Insulation | 8/20/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 8/20/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Drywall Nailing | 8/25/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/25/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/26/2020 | Approved | CRAIG DAVIS |
| HVAC-Final | 9/9/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 10/15/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Gas Test | 10/15/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 10/15/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/20/2020 | Approved | ENRIQUE MIRELES |
| Gas Test | 10/26/2020 | No Access for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 10/26/2020 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 10/26/2020 | No Access for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 10/26/2020 | No Access for Inspection | ENRIQUE MIRELES |
| Gas Test | 10/30/2020 | Approved | ENRIQUE MIRELES |
| Green Building Final | 10/30/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 10/30/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 10/30/2020 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/30/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 11/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 11/24/2020 | Corrections Issued | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/24/2020 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 11/24/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 12/1/2020 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 12/1/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 12/7/2020 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 12/7/2020 | Approved | ENRIQUE MIRELES |