8352 S CHASE AVE 90045

Certificate Information: 8352 S CHASE AVE 90045

Application / Permit
19014-30000-06823
Plan Check / Job No.
B19WL07025
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition/remodel to (e) 1-story SFD.
Permit Issued
Issued on 1/11/2021
Issuing Office
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/31/2019 VLADIMIR ARUTYUNYAN
Green Plans Picked Up 1/3/2020 APPLICANT
Corrections Issued 1/8/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 1/17/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/2/2020 VLADIMIR ARUTYUNYAN
Applicant returned to address corrections 7/27/2020 VLADIMIR ARUTYUNYAN
Plan Check Approved 12/30/2020 VLADIMIR ARUTYUNYAN
Issued 1/11/2021 APPLICANT
Building Plans Picked Up 1/14/2021 APPLICANT
CofO in Progress 9/14/2021 BRENDAN LOONEY
Permit Finaled 9/21/2021 KENNETH NAGLE
CofO Issued 9/21/2021 KENNETH NAGLE
Permit Finaled 9/21/2021 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/20/2020 ERIK BEASLEY
Sewer availability Cleared 2/20/2020 ERIK BEASLEY
Green Code Cleared 2/26/2020 DONALD CRICHLOW
Low Impact Development Cleared 5/26/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 6/1/2020 DINAH GARIN

Contact Information

Contractor Forsyth Construction Inc; Lic. No.: 560243-B 578 WASHINGTON BLVD #377      MARINA DEL REY, CA 90292
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/25/2021 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/3/2021 Approved EVAN COOPER
Underground Mechanical 2/3/2021 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 3/31/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 3/31/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Partial Approval BRENDAN LOONEY
Green Building Rough 3/31/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 3/31/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 3/31/2021 Not Ready for Inspection BRENDAN LOONEY
Deputy Wood Construction 4/6/2021 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 4/7/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 4/7/2021 Corrections Issued BRENDAN LOONEY
Insulation 5/5/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 5/5/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 5/5/2021 Approved BRENDAN LOONEY
Shower Pan 5/5/2021 Approved BRENDAN LOONEY
Drywall Nailing 5/11/2021 Approved BRENDAN LOONEY
ELECTRICAL-Final 8/5/2021 Corrections Issued BRENDAN LOONEY
Service/Power Release 8/5/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Final 8/11/2021 Corrections Issued BRENDAN LOONEY
Service/Power Release 8/11/2021 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 8/23/2021 Approved BRENDAN LOONEY
Final 8/23/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 8/23/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 8/23/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 8/23/2021 SGSOV Approved BRENDAN LOONEY
Service/Power Release 8/23/2021 Approved BRENDAN LOONEY
Smoke Detectors 8/23/2021 Approved BRENDAN LOONEY
Final 9/10/2021 OK to Issue CofO BRENDAN LOONEY
Green Building Final 9/10/2021 Approved BRENDAN LOONEY