4058 S MICHAEL AVE 90066

Certificate Information: 4058 S MICHAEL AVE 90066

Application / Permit
19014-30000-06811
Plan Check / Job No.
B19WL07011
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2-story addition to (e) SFD
Permit Issued
Issued on 1/22/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Green Plans Picked Up 1/2/2019 APPLICANT
Submitted 12/16/2019 APPLICANT
Assigned to Plan Check Engineer 12/31/2019 REZA HAGHIGHAT
Corrections Issued 1/6/2020 REZA HAGHIGHAT
Quality Review Completed 1/17/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 1/17/2020 APPLICANT
Plan Check Approved 1/21/2020 REZA HAGHIGHAT
Issued 1/22/2020 LADBS
CofO in Progress 9/29/2020 PIERRE VEGA
CofO in Progress 9/29/2020 PIERRE VEGA
CofO Issued 9/29/2020 VINCENT COTTON
Permit Finaled 9/29/2020 VINCENT COTTON

Permit Application Clearance Information

Green Code Cleared 1/8/2020 DONALD CRICHLOW
Low Impact Development Cleared 1/10/2020 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 1/16/2020 ANTHONY MAINEZ
Permit Cleared 1/16/2020 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 1/16/2020 ANTHONY MAINEZ
Sewer availability Cleared 1/16/2020 ANTHONY MAINEZ
Trees in Parkway Cleared 1/17/2020 ADRIAN SANCHEZ
Miscellaneous Cleared 1/21/2020 DENZEL HENDERSON

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Southland Building & Remodel Company; Lic. No.: 894311-B 1324 WEST ROSECRANS AVENUE      COMPTON, CA 90222
Engineer Namdar,, Mansour Tom; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/19/2020 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 2/26/2020 Approved DAVID FEILER
Footing/Foundation/Slab 2/26/2020 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/10/2020 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 3/12/2020 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/2/2020 Partial Approval DAVID FEILER
HVAC-Rough 4/15/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 4/15/2020 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 4/16/2020 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/16/2020 Approved JUAN VALENZUELA
Green Building Rough 4/16/2020 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 4/16/2020 Partial Approval JUAN VALENZUELA
Shower Pan 4/16/2020 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 4/21/2020 Approved DAVID FEILER
Green Building Rough 4/21/2020 Approved DAVID FEILER
PLUMBING-Rough 4/21/2020 Approved DAVID FEILER
Wood Frame 4/21/2020 Approved DAVID FEILER
Insulation 4/24/2020 Approved DAVID FEILER
Drywall Nailing 4/28/2020 Approved DAVID FEILER
Interior/Exterior Lathing 4/28/2020 Approved DAVID FEILER
Gas Test 9/10/2020 Approved DAVID HEINE
ELECTRICAL-Final 9/25/2020 Approved ENRIQUE MIRELES
Final 9/25/2020 Corrections Issued ENRIQUE MIRELES
Green Building Final 9/25/2020 Approved ENRIQUE MIRELES
HVAC-Final 9/25/2020 Approved ENRIQUE MIRELES
PLUMBING-Final 9/25/2020 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/25/2020 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 9/25/2020 Approved ENRIQUE MIRELES
Smoke Detectors 9/25/2020 Approved ENRIQUE MIRELES
Final 9/29/2020 OK to Issue CofO PIERRE VEGA