3784 S BOISE AVE 90066

Certificate Information: 3784 S BOISE AVE 90066

Application / Permit
19014-30000-06783
Plan Check / Job No.
B19WL06972
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ADD NEW STORAGE ROOM AT REAR.
Permit Issued
Issued on 10/17/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2019 APPLICANT
Assigned to Plan Check Engineer 12/18/2019 REZA HAGHIGHAT
Corrections Issued 12/19/2019 REZA HAGHIGHAT
Building Plans Picked Up 1/7/2020 APPLICANT
Plan Check Approved 10/16/2023 ALFREDO JARA
Issued 10/17/2023 APPLICANT
CofO in Progress 7/17/2025 MICHAEL ALLEN
Permit Finaled 7/19/2025 RICHARD STEINBACH
CofO Issued 7/19/2025 RICHARD STEINBACH
Permit Finaled 7/19/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/27/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/27/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 1/27/2020 DINAH GARIN
Sewer availability Cleared 1/27/2020 DINAH GARIN
Construction near power lines Cleared 12/28/2020 RIDWAN HARDY
Hydrant and Access approval Cleared 1/4/2021 MATTHEW CRAIG
Grading Pre-Inspection Cleared 10/16/2023 REZA HAGHIGHAT

Contact Information

Architect Howell,, Ronald Edwards; Lic. No.: C21122 P O BOX 661007      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/16/2023 Not Ready for Inspection JESUS RODRIGUEZ
Pre-Inspection 3/7/2024 Not Ready for Inspection JESUS RODRIGUEZ
Pre-Inspection 7/10/2024 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 9/26/2024 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 10/16/2024 Approved JESUS PINEDA
Underground Mechanical 10/16/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 12/20/2024 Approved BOBBY KEY
Special/Order Compliance 12/20/2024 Partial Inspection JAYLIN GRAVITTE
Floor/Roof Diaphrgm/Shear Wall 12/24/2024 Approved JESUS PINEDA
HVAC-Rough 12/24/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 1/16/2025 Approved JESUS PINEDA
Green Building Rough 1/16/2025 Approved JESUS PINEDA
Insulation 1/16/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 1/16/2025 Approved JESUS PINEDA
PLUMBING-Rough 1/16/2025 Approved JESUS PINEDA
Drywall Nailing 1/23/2025 Approved BOBBY KEY
Special/Order Compliance 1/23/2025 Partial Inspection JAYLIN GRAVITTE
ELECTRICAL-Final 6/13/2025 Conditional Approval MICHAEL ALLEN
Final 6/13/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 6/13/2025 Approved MICHAEL ALLEN
HVAC-Final 6/13/2025 Conditional Approval MICHAEL ALLEN
PLUMBING-Final 6/13/2025 Conditional Approval MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 6/13/2025 Conditional Approval MICHAEL ALLEN
Final 6/24/2025 Corrections Issued MICHAEL ALLEN
Smoke Detectors 6/24/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 7/15/2025 Approved MICHAEL ALLEN
Final 7/15/2025 OK to Issue CofO MICHAEL ALLEN
HVAC-Final 7/15/2025 Approved MICHAEL ALLEN
PLUMBING-Final 7/15/2025 Approved MICHAEL ALLEN