1834 N WESTERLY TER 90026
Certificate Information: 1834 N WESTERLY TER 90026
- Application / Permit
- 19014-30000-06779
- Plan Check / Job No.
- B19WL06967
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and addition to (e) SFD, 2-story over basement.
- Permit Issued
- Issued on 3/22/2021
- Issuing Office
- Current Status
- CofO Issued on 3/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 12/30/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 1/13/2020 | FELIX FIGUEROA |
| Applicant returned to address corrections | 6/10/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 7/15/2020 | APPLICANT |
| Applicant returned to address corrections | 8/4/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/25/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 11/17/2020 | APPLICANT |
| Applicant returned to address corrections | 1/13/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 3/9/2021 | KAMRAN GHOTBI RAVANDI |
| Issued | 3/22/2021 | APPLICANT |
| CofO in Progress | 3/10/2025 | HAMIK HARTOUNIAN |
| Permit Finaled | 3/12/2025 | DEROLD HAUFF |
| CofO Issued | 3/12/2025 | DEROLD HAUFF |
| Permit Finaled | 3/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 1/14/2020 | DENNIS BRAGIN |
| Sewer availability | Cleared | 1/14/2020 | DENNIS BRAGIN |
| BHO/Hillside ordinance | Cleared | 1/31/2020 | THAN WIN |
| BHO/Hillside ordinance | Cleared | 4/21/2020 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 4/29/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2020 | CELINA MORENO |
| Green Code | Cleared | 7/15/2020 | DONALD CRICHLOW |
| Trees in Parkway | Cleared | 7/21/2020 | JOHN KIM |
| Low Impact Development | Cleared | 12/13/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/23/2020 | RENZ SORIANO |
Contact Information
| Architect | Bestor,, Barbara A; Lic. No.: C26132 | 2030 HYPERION AVENUE LOS ANGELES, CA 90027 |
| Contractor | Caire John Construction Inc; Lic. No.: 626684-B | 2028 LOMBARDY DR LA CANADA, CA 91011 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/14/2021 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/16/2021 | Corrections Issued | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 9/20/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/20/2021 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 9/22/2021 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/19/2021 | Partial Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 10/26/2021 | Partial Approval | RUBEN SALAS |
| Deputy Reinf. Concrete | 2/28/2022 | Conditional Approval | RUBEN SALAS |
| Piling/Pier/Caisson | 4/13/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 4/18/2022 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 5/4/2022 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/6/2022 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 5/9/2022 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 5/24/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 5/25/2022 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Steel/Welding | 7/20/2022 | Conditional Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Partial Approval | THOMAS LOGRASSO |
| Structural Steel Frame | 8/2/2022 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 8/22/2022 | Partial Approval | RUBEN SALAS |
| Deputy Other (see comments) | 8/25/2022 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 9/6/2022 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Shotcrete | 9/14/2022 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/18/2022 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 11/18/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 12/8/2022 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/9/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 12/12/2022 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 2/1/2023 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 2/1/2023 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/22/2023 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 3/21/2023 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/22/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 3/28/2023 | Partial Approval | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 5/8/2023 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Wood Construction | 5/9/2023 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 5/9/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2023 | Partial Approval | THOMAS LOGRASSO |
| HVAC-Rough | 5/9/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 5/9/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/22/2023 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/31/2023 | Approved | THOMAS LOGRASSO |
| Green Building Rough | 5/31/2023 | Approved | THOMAS LOGRASSO |
| Insulation | 5/31/2023 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 5/31/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 6/12/2023 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/12/2023 | Partial Approval | THOMAS LOGRASSO |
| Drywall Nailing | 6/26/2023 | Partial Approval | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 6/28/2023 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 10/31/2023 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 11/1/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/2/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Drywall Nailing | 4/5/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 4/5/2024 | Approved | THOMAS LOGRASSO |
| Final | 4/5/2024 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 4/5/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Final | 4/5/2024 | Approved | THOMAS LOGRASSO |
| PLUMBING-Final | 4/5/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 4/5/2024 | Approved | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 6/21/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 3/3/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |