3356 S MCLAUGHLIN AVE 90066
Certificate Information: 3356 S MCLAUGHLIN AVE 90066
- Application / Permit
- 19014-30000-06772
- Plan Check / Job No.
- B19WL06959
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- Addition & conversion from (e) det. garage w/ att. storage to det. garage w/ att. ALQ.
- Permit Issued
- Issued on 4/1/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | REZA HAGHIGHAT |
| Corrections Issued | 12/18/2019 | REZA HAGHIGHAT |
| Building Plans Picked Up | 12/24/2019 | APPLICANT |
| Plan Check Approved | 1/6/2020 | REZA HAGHIGHAT |
| Issued | 4/1/2020 | LADBS |
| CofO in Progress | 11/5/2020 | EVAN COOPER |
| CofO Issued | 11/17/2020 | VINCENT COTTON |
| Permit Finaled | 11/17/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/6/2020 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2020 | EMIL KYUPELYAN |
| Grading Pre-Inspection | Cleared | 1/6/2020 | REZA HAGHIGHAT |
| Hydrant and Access approval | Cleared | 1/6/2020 | JEREMY CARTER |
| Roof/Waste drainage to street | Cleared | 1/6/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 1/6/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | L E A D Enterprises Inc; Lic. No.: 955824-B | 6803 YARMOUTH AVENUE RESEDA, CA 91335 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 1836 PARNELL AVE 202 LOS ANGELES, CA 90025 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/16/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/16/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/29/2020 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 7/2/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Green Building Rough | 7/2/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Wood Frame | 7/2/2020 | Partial Approval | JUSTIN CURTIS |
| BUILDING-Rough-Frame | 8/13/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/13/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 8/13/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/13/2020 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/18/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2020 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 8/18/2020 | Approved | EVAN COOPER |
| HVAC-Rough | 8/24/2020 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 8/24/2020 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 8/26/2020 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/26/2020 | Approved | EVAN COOPER |
| Green Building Rough | 8/26/2020 | Approved | EVAN COOPER |
| HVAC-Rough | 8/26/2020 | Approved | EVAN COOPER |
| Insulation | 8/26/2020 | Approved | EVAN COOPER |
| Drywall Nailing | 8/31/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 8/31/2020 | Approved | EVAN COOPER |
| Shower Pan | 8/31/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 10/9/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 10/9/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 10/9/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/9/2020 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 10/9/2020 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/16/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 10/16/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 10/16/2020 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 10/16/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 10/16/2020 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/16/2020 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Service/Power Release | 10/16/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 10/29/2020 | Partial Approval | EVAN COOPER |
| PLUMBING-Final | 10/29/2020 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 10/29/2020 | SGSOV Approved | EVAN COOPER |