7556 S MCCONNELL AVE 90045

Certificate Information: 7556 S MCCONNELL AVE 90045

Application / Permit
19014-30000-06726
Plan Check / Job No.
B19WL06897
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2nd story addition to (e) 1 story s.f.d., add an att. 2-car garage
Permit Issued
Issued on 6/30/2020
Issuing Office
Current Status
CofO Issued on 4/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 REZA HAGHIGHAT
Corrections Issued 12/30/2019 REZA HAGHIGHAT
Quality Review Completed 1/10/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/12/2020 REZA HAGHIGHAT
Applicant returned to address corrections 4/17/2020 REZA HAGHIGHAT
Applicant returned to address corrections 5/14/2020 REZA HAGHIGHAT
Applicant returned to address corrections 5/18/2020 REZA HAGHIGHAT
Green Plans Picked Up 6/9/2020 APPLICANT
Plan Check Approved 6/12/2020 REZA HAGHIGHAT
Plan Check Approved 6/29/2020 REZA HAGHIGHAT
Issued 6/30/2020 APPLICANT
Building Plans Picked Up 9/15/2020 APPLICANT
CofO in Progress 4/19/2023 BOBBY KEY
Permit Finaled 4/20/2023 DANIEL ORRANTE
CofO Issued 4/20/2023 DANIEL ORRANTE
Permit Finaled 4/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2020 DINAH GARIN
Sewer availability Cleared 5/6/2020 DINAH GARIN
Low Impact Development Cleared 5/27/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/27/2020 DINAH GARIN
Grading Pre-Inspection Cleared 6/12/2020 REZA HAGHIGHAT
Green Code Cleared 6/12/2020 RICHARD GARCIA

Contact Information

Contractor H T Builders; Lic. No.: 1051585-B 223 N GLENDORA AVENUE      GLENDORA, CA 91741
Engineer Manlangit,, Vicente Balingasa; Lic. No.: C75499 20626 HAYNES ST      WINNETKA, CA 91306

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/17/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 9/17/2020 Not Ready for Inspection JUAN VALENZUELA
METHANE-Barrier 9/17/2020 Not Ready for Inspection JUAN VALENZUELA
METHANE-Subgrade 9/17/2020 Not Ready for Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/24/2020 Approved JUAN VALENZUELA
Footing/Foundation/Slab 9/24/2020 Approved JUAN VALENZUELA
METHANE-Barrier 9/24/2020 Approved JUAN VALENZUELA
METHANE-Subgrade 9/24/2020 Approved JUAN VALENZUELA
PLUMBING-Rough 10/21/2020 Partial Approval JUAN VALENZUELA
Underground Mechanical 10/21/2020 Partial Inspection JUAN VALENZUELA
Wood Frame 10/21/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Partial Approval JUAN VALENZUELA
HVAC-Rough 6/23/2021 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 6/23/2021 Corrections Issued BRENDAN LOONEY
Underground Mechanical 6/23/2021 Not Ready for Inspection BRENDAN LOONEY
Wood Frame 6/23/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 2/3/2022 Approved BOBBY KEY
HVAC-Rough 2/3/2022 Approved BOBBY KEY
PLUMBING-Rough 2/3/2022 Approved BOBBY KEY
Sewer 2/3/2022 Approved BOBBY KEY
Underground Mechanical 2/3/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/24/2022 Corrections Issued BOBBY KEY
Deputy Wood Construction 5/9/2022 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 6/1/2022 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Approved BOBBY KEY
Green Building Rough 6/1/2022 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 6/6/2022 Corrections Issued BOBBY KEY
Green Building Rough 6/6/2022 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 6/6/2022 Not Ready for Inspection BOBBY KEY
Shower Pan 6/6/2022 Not Ready for Inspection BOBBY KEY
BUILDING-Rough-Frame 6/28/2022 Approved BOBBY KEY
Green Building Rough 6/28/2022 Approved BOBBY KEY
Insulation 6/28/2022 Approved BOBBY KEY
Interior/Exterior Lathing 6/28/2022 Partial Approval BOBBY KEY
Shower Pan 6/28/2022 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 7/6/2022 Approved JESUS RODRIGUEZ
Shower Pan 7/6/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 7/13/2022 Approved HERBERT GIRON
Gas Test 1/31/2023 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 1/31/2023 SGSOV Not Ready EVAN COOPER
Smoke Detectors 1/31/2023 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Approved BOBBY KEY
Underground Mechanical 2/3/2023 Partial Approval BOBBY KEY
ELECTRICAL-Final 3/3/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 3/3/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 3/17/2023 Corrections Issued HERBERT GIRON
Final 3/17/2023 Corrections Issued HERBERT GIRON
Green Building Final 3/17/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Final 3/17/2023 Not Ready for Inspection HERBERT GIRON
METHANE-Final 3/17/2023 Approved HERBERT GIRON
PLUMBING-Final 3/17/2023 Corrections Issued HERBERT GIRON
Service/Power Release 3/17/2023 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 3/17/2023 Approved HERBERT GIRON
Gas Test 3/23/2023 Approved BOBBY KEY
ELECTRICAL-Final 4/18/2023 Approved BOBBY KEY
Final 4/18/2023 Corrections Issued BOBBY KEY
Green Building Final 4/18/2023 Approved BOBBY KEY
HVAC-Final 4/18/2023 Approved BOBBY KEY
PLUMBING-Final 4/18/2023 Not Ready for Inspection BOBBY KEY
Service/Power Release 4/18/2023 Not Ready for Inspection BOBBY KEY
Final 4/19/2023 OK to Issue CofO BOBBY KEY
Service/Power Release 4/19/2023 Approved BOBBY KEY