11333 W KELOWNA ST 91342

Certificate Information: 11333 W KELOWNA ST 91342

Application / Permit
19014-30000-06697
Plan Check / Job No.
B19WL06852
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDITION TO (E) 2-STORY SFD W/ ATT. GARAGE TO ADD A LAUNDRY ROOM & BATHROOM (216 SF), & EXTEND (E) ATT. GARAGE (249 SF).
Permit Issued
Issued on 3/12/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 ALFREDO JARA
Corrections Issued 12/13/2019 ALFREDO JARA
Building Plans Picked Up 12/19/2019 APPLICANT
Plan Check Approved 3/9/2020 REZA HAGHIGHAT
Issued 3/12/2020 LADBS
CofO in Progress 9/4/2020 MICHEL ABAJAN
Permit Finaled 5/10/2022 MICHAEL SMITH
CofO Issued 5/10/2022 MICHAEL SMITH
Permit Finaled 5/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/9/2020 MAHELET GEBEYHU
Grading Pre-Inspection Cleared 3/9/2020 ALFREDO JARA
Roof/Waste drainage to street Cleared 3/9/2020 MAHELET GEBEYHU

Contact Information

Contractor Owner-Builder       ,
Engineer Kiledjian,, George Zohrab; Lic. No.: C74761 11447 VIKING AVE      NORTHRIDGE, CA 91326

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/31/2020 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 4/13/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 4/24/2020 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 5/19/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/19/2020 Approved MICHEL ABAJAN
Green Building Rough 5/19/2020 Approved MICHEL ABAJAN
HVAC-Rough 5/19/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 5/19/2020 Approved MICHEL ABAJAN
Insulation 6/2/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/2/2020 Approved MICHEL ABAJAN
Drywall Nailing 6/4/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 9/4/2020 Approved MICHEL ABAJAN
Final 9/4/2020 OK to Issue CofO MICHEL ABAJAN
Green Building Final 9/4/2020 Approved MICHEL ABAJAN
HVAC-Final 9/4/2020 Approved MICHEL ABAJAN
PLUMBING-Final 9/4/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/4/2020 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 9/4/2020 Approved MICHEL ABAJAN