2257 S COLBY AVE 90064
Certificate Information: 2257 S COLBY AVE 90064
- Application / Permit
- 19014-30000-06692
- Plan Check / Job No.
- B19WL06845
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TI, EXPAND 2ND FLOOR DECK, PARTITIONS, MULTISTALL RESTROOMS, NEW SKYLIGHT, NEW EXTERIOR DOORS AND WINDOWS and restripe portion of parking lot.
- Permit Issued
- Issued on 5/19/2020
- Issuing Office
- Current Status
- CofO Issued on 1/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2019 | TARIK SAOUD |
| Green Plans Picked Up | 12/27/2019 | APPLICANT |
| Corrections Issued | 12/30/2019 | TARIK SAOUD |
| Quality Review Completed | 1/3/2020 | FELIX FIGUEROA |
| Disabled Access Plans Picked Up | 1/31/2020 | APPLICANT |
| Plan Check Approved | 3/5/2020 | TARIK SAOUD |
| Issued | 5/19/2020 | APPLICANT |
| Building Plans Picked Up | 11/24/2020 | APPLICANT |
| CofO in Progress | 1/18/2022 | JOHN DODGE |
| Permit Finaled | 1/26/2022 | DAVID TSAU |
| CofO Issued | 1/26/2022 | DAVID TSAU |
| Permit Finaled | 1/26/2022 | DAVID TSAU |
Permit Application Clearance Information
| DAS Clearance | Cleared | 2/13/2020 | SOMKIAT SUPANYACHOTSKUL |
| CPC | Cleared | 2/18/2020 | JASON CHAN |
| Construction near power lines | Cleared | 2/18/2020 | OSCAR CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 2/18/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/18/2020 | JEANIE LAM |
| Internal circulation | Cleared | 2/20/2020 | VALERIA CEJA |
| Specific Plan | Cleared | 2/20/2020 | VALERIA CEJA |
| Green Code | Cleared | 2/21/2020 | RICHARD GARCIA |
Contact Information
| Architect | Thoeny,, Bret Felix; Lic. No.: C21047 | 43 HALDEMAN ROAD SANTA MONICA, CA 90402 |
| Contractor | City Constructors Inc; Lic. No.: 834591-B | 3125 N BROADWAY LOS ANGELES, CA 90031 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/25/2020 | Conditional Approval | JOHN DODGE |
| Deputy Drilled-In Anchors | 6/26/2020 | Approved | JOHN DODGE |
| Deputy Reinf. Concrete | 6/26/2020 | Approved | JOHN DODGE |
| Pre-Inspection | 6/26/2020 | Approved | JOHN DODGE |
| Reinforced Concrete Frame | 7/2/2020 | Partial Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 7/6/2020 | Conditional Approval | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 7/23/2020 | Not Ready for Inspection | JOHN DODGE |
| Deputy Drilled-In Anchors | 7/24/2020 | Approved | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 7/24/2020 | Approved | JOHN DODGE |
| Deputy Reinf. Concrete | 7/27/2020 | Conditional Approval | JOHN DODGE |
| Footing/Foundation/Slab | 7/29/2020 | Partial Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 7/30/2020 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 8/14/2020 | Partial Approval | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 9/28/2020 | No Access for Inspection | JOHN DODGE |
| Light Gage Steel Frame | 9/28/2020 | Conditional Approval | JOHN DODGE |
| Wood Frame | 10/6/2020 | Not Ready for Inspection | JOHN DODGE |
| Insulation | 10/13/2020 | Partial Approval | JOHN DODGE |
| Wood Frame | 10/13/2020 | No Access for Inspection | JOHN DODGE |
| Drywall Nailing | 10/23/2020 | Not Ready for Inspection | JOHN DODGE |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Not Ready for Inspection | JOHN DODGE |
| Footing/Foundation/Slab | 10/23/2020 | Partial Approval | JOHN DODGE |
| Insulation | 10/23/2020 | Partial Approval | JOHN DODGE |
| Green Building Rough | 10/26/2020 | Approved | JOHN DODGE |
| Insulation | 10/26/2020 | Approved | JOHN DODGE |
| Light Gage Steel Frame | 10/26/2020 | Approved | JOHN DODGE |
| Wood Frame | 10/27/2020 | Conditional Approval | JOHN DODGE |
| Insulation | 10/28/2020 | Not Ready for Inspection | JOHN DODGE |
| Special/Order Compliance | 10/28/2020 | Approved | TED RIES |
| Wood Frame | 10/28/2020 | Partial Approval | JOHN DODGE |
| Wood Frame | 11/4/2020 | Corrections Issued | JOHN DODGE |
| Special/Order Compliance | 11/5/2020 | Approved | JOHN DODGE |
| Drywall Nailing | 11/10/2020 | Not Ready for Inspection | JOHN DODGE |
| Light Gage Steel Frame | 11/10/2020 | Not Ready for Inspection | JOHN DODGE |
| Wood Frame | 11/10/2020 | Partial Inspection | JOHN DODGE |
| Deputy Wood Construction | 11/12/2020 | Conditional Approval | JOHN DODGE |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2020 | Partial Approval | JOHN DODGE |
| Insulation | 11/13/2020 | Partial Approval | JOHN DODGE |
| Wood Frame | 11/13/2020 | Partial Approval | JOHN DODGE |
| Drywall Nailing | 11/16/2020 | Partial Approval | JOHN DODGE |
| Insulation | 11/16/2020 | Partial Approval | JOHN DODGE |
| Insulation | 11/18/2020 | Partial Approval | JOHN DODGE |
| Insulation | 11/23/2020 | Partial Approval | JOHN DODGE |
| Deputy Wood Construction | 11/24/2020 | Conditional Approval | JOHN DODGE |
| Wood Frame | 12/3/2020 | Approved | JOHN DODGE |
| Drywall Nailing | 12/4/2020 | Partial Approval | JOHN DODGE |
| Excavation/Setback/Form/Re-Bar | 12/30/2020 | Approved | JOHN DODGE |
| Special/Order Compliance | 1/4/2021 | Approved | JOHN DODGE |
| Light Gage Steel Frame | 1/28/2021 | Not Ready for Inspection | GRANT WOODS |
| Light Gage Steel Frame | 2/5/2021 | Not Ready for Inspection | JOHN DODGE |
| Deputy Reinf. Concrete | 2/11/2021 | Conditional Approval | JOHN DODGE |
| Light Gage Steel Frame | 2/11/2021 | Partial Approval | JOHN DODGE |
| Insulation | 2/16/2021 | Partial Approval | JOHN DODGE |
| Light Gage Steel Frame | 2/16/2021 | Partial Approval | JOHN DODGE |
| Structural Steel Frame | 2/16/2021 | Approved | JOHN DODGE |
| Drywall Nailing | 2/18/2021 | Partial Approval | PAUL DAVIDSON |
| Drywall Nailing | 2/23/2021 | Partial Approval | JOHN DODGE |
| Wood Frame | 4/8/2021 | Not Ready for Inspection | JOHN DODGE |
| Drywall Nailing | 4/15/2021 | Approved | JOHN DODGE |
| Insulation | 4/29/2021 | Partial Approval | JOHN DODGE |
| Interior/Exterior Lathing | 4/29/2021 | No Access for Inspection | JOHN DODGE |
| Wood Frame | 4/29/2021 | Conditional Approval | JOHN DODGE |
| Insulation | 5/4/2021 | Partial Approval | JOHN DODGE |
| Interior/Exterior Lathing | 5/4/2021 | Partial Approval | JOHN DODGE |
| Drywall Nailing | 5/12/2021 | Partial Approval | ALAN NOVAK |
| Drywall Nailing | 5/19/2021 | Partial Approval | JOHN DODGE |
| Interior/Exterior Lathing | 5/19/2021 | Approved | JOHN DODGE |
| Insulation | 6/2/2021 | Not Ready for Inspection | JOHN DODGE |
| Light Gage Steel Frame | 6/2/2021 | Partial Approval | JOHN DODGE |
| Drywall Nailing | 6/7/2021 | Partial Inspection | JOHN DODGE |
| Drywall Nailing | 6/8/2021 | Partial Approval | JOHN DODGE |
| Insulation | 6/8/2021 | Approved | JOHN DODGE |
| Pre-Inspection | 6/8/2021 | Approved | JOHN DODGE |
| Interior/Exterior Lathing | 6/9/2021 | Approved | JOHN DODGE |
| Drywall Nailing | 6/14/2021 | Approved | JOHN DODGE |
| Pre-Inspection | 6/23/2021 | Approved | JOHN DODGE |
| Deputy Wood Construction | 7/21/2021 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 7/30/2021 | Conditional Approval | JOHN DODGE |
| Deputy Reinf. Concrete | 8/2/2021 | Conditional Approval | JOHN DODGE |
| Masonry Wall/Backfill | 8/10/2021 | Approved | JOHN DODGE |
| Footing/Foundation/Slab | 8/12/2021 | Approved | JOHN DODGE |
| Pre-Inspection | 8/12/2021 | Partial Inspection | JOHN DODGE |
| Pre-Inspection | 8/17/2021 | Approved | JOHN DODGE |
| Final | 8/23/2021 | OK to Issue CofO | JOHN DODGE |
| Green Building Final | 8/23/2021 | Approved | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 8/23/2021 | SGSOV Approved | JOHN DODGE |
| Smoke Detectors | 8/23/2021 | Approved | JOHN DODGE |
| Wood Frame | 8/23/2021 | Approved | JOHN DODGE |
| Final | 9/1/2021 | Conditional Approval | JOHN DODGE |
| Special/Order Compliance | 12/28/2021 | No Access for Inspection | JOHN DODGE |