4249 N BECK AVE 91604
Certificate Information: 4249 N BECK AVE 91604
- Application / Permit
- 19014-30000-06667
- Plan Check / Job No.
- B19WL06817
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and addition to (e) living room & install (n) door system at (e) single family dwelling. Per engineering detail.
- Permit Issued
- Issued on 2/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | MANUEL GARCIA |
| Corrections Issued | 12/17/2019 | MANUEL GARCIA |
| Building Plans Picked Up | 12/19/2019 | APPLICANT |
| Applicant returned to address corrections | 1/30/2020 | REZA HAGHIGHAT |
| Plan Check Approved | 2/11/2020 | ALFREDO JARA |
| Issued | 2/12/2020 | LADBS |
| CofO in Progress | 5/11/2021 | DANIEL ORRANTE |
| Permit Finaled | 5/12/2021 | MICHAEL SMITH |
| CofO Issued | 5/12/2021 | MICHAEL SMITH |
| Permit Finaled | 5/12/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2019 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | DINAH GARIN |
| Sewer availability | Cleared | 12/19/2019 | DINAH GARIN |
| ZI | Cleared | 1/9/2020 | JOE LUCKEY |
Contact Information
| Architect | Donner,, Devin F; Lic. No.: C25868 | 9009 BEVERLY BLVD_#102 WEST HOLLYWOOD, CA 90048 |
| Contractor | Middleton Building And Remodeling; Lic. No.: 912321-B | 13636 VENTURA BLVD STE 168 SHERMAN OAKS, CA 91423 |
| Engineer | Lotfi,, Fariborz Frank; Lic. No.: C49359 | 1547 PALISADES DR PACIFIC PALISADES, CA 90272 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/28/2020 | Conditional Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 8/21/2020 | Conditional Approval | THOMAS FINNILA |
| Deputy Wood Construction | 8/21/2020 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/2/2020 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/2/2020 | Approved | THOMAS FINNILA |
| Green Building Rough | 9/2/2020 | Approved | THOMAS FINNILA |
| Insulation | 9/16/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/16/2020 | Corrections Issued | THOMAS FINNILA |
| Drywall Nailing | 10/7/2020 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/7/2020 | Approved | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/26/2021 | Approved | THOMAS FINNILA |
| Smoke Detectors | 3/26/2021 | Corrections Issued | THOMAS FINNILA |
| Final | 4/5/2021 | Corrections Issued | DANIEL ORRANTE |
| Green Building Final | 4/5/2021 | Approved | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Approved | DANIEL ORRANTE |
| Final | 5/11/2021 | OK to Issue CofO | DANIEL ORRANTE |
| Smoke Detectors | 5/11/2021 | Approved | DANIEL ORRANTE |