6703 N VALJEAN AVE 91406

Certificate Information: 6703 N VALJEAN AVE 91406

Application / Permit
19014-30000-06654
Plan Check / Job No.
B19WL06797
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(7) Garage - Private
Work Description
New garage building
Permit Issued
Issued on 7/13/2021
Issuing Office
Current Status
CofO Issued on 8/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 2/6/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 2/13/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 6/17/2020 APPLICANT
Green Plans Picked Up 7/9/2020 APPLICANT
Disabled Access Plans Picked Up 12/15/2020 APPLICANT
Plan Check Approved 5/4/2021 CHIHARU SUZUKI
Issued 7/13/2021 APPLICANT
CofO in Progress 7/26/2023 CAMERON CHABAN
CofO in Progress 8/8/2023 CAMERON CHABAN
CofO Issued 8/9/2023 RICKEY JACKSON
Permit Finaled 8/9/2023 RICKEY JACKSON

Permit Application Clearance Information

Internal circulation Cleared 4/29/2020 BRANDON WILSON
Eng Process Fee Ord 176,300 Cleared 5/8/2020 LEE GUILBEAUX
Highway dedication Cleared 5/8/2020 LEE GUILBEAUX
Sewer availability Cleared 5/8/2020 LEE GUILBEAUX
Permit Cleared 6/17/2020 LEE GUILBEAUX
DAS Clearance Cleared 7/14/2020 SOMKIAT SUPANYACHOTSKUL
Hydrant and Access approval Cleared 9/4/2020 KURT CORRAL
Low Impact Development Cleared 10/9/2020 JORGE MEJIA LEMUS
Green Code Cleared 10/29/2020 RICHARD GARCIA
Roof/Waste drainage to street Cleared 11/4/2020 LEE GUILBEAUX
"Q" conditions Cleared 11/24/2020 NOAH MCCOY
"T" removal Cleared 11/24/2020 NOAH MCCOY
ZI Cleared 11/24/2020 NOAH MCCOY

Contact Information

Architect Packman,, Shannon Paul; Lic. No.: C31245 250 LUPE AVENUE      NEWBURY PARK, CA 91320
Contractor Gluck Development Company Inc; Lic. No.: 503281-B 26901 AGOURA ROAD   SUITE 100    CALABASAS, CA 91301
Engineer Provenghi,, Steven Guido; Lic. No.: S3888 8522 ACACIA DR      CYPRESS, CA 90630

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/21/2022 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 1/24/2022 Conditional Approval JOHN KITCKO
Deputy Steel/Welding 2/8/2022 Approved JOHN KITCKO
Deputy Reinf. Masonry 2/16/2022 Conditional Approval JOHN KITCKO
Deputy Reinf. Masonry 2/17/2022 Conditional Approval JOHN KITCKO
Masonry Wall/Backfill 2/22/2022 Partial Approval CAMERON CHABAN
Footing/Foundation/Slab 3/1/2022 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 3/10/2022 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 3/18/2022 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 4/1/2022 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 4/14/2022 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 4/21/2022 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 8/9/2022 Conditional Approval CAMERON CHABAN
Special/Order Compliance 3/8/2023 Partial Inspection JOHN KITCKO
Special/Order Compliance 3/23/2023 Partial Inspection JOHN KITCKO
Final 7/17/2023 OK to Issue CofO CAMERON CHABAN
Footing/Foundation/Slab 7/17/2023 Approved CAMERON CHABAN
Green Building Final 7/17/2023 Approved CAMERON CHABAN
Green Building Rough 7/17/2023 Approved CAMERON CHABAN
Reinforced Masonry Frame 7/17/2023 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 7/17/2023 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 7/17/2023 Approved CAMERON CHABAN
Final 7/20/2023 OK to Issue CofO CAMERON CHABAN