1301 W 22ND ST 90007
Certificate Information: 1301 W 22ND ST 90007
- Application / Permit
- 19014-30000-06641
- Plan Check / Job No.
- B19WL06783
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2nd floor addition to s.f.d. 650 sf
- Permit Issued
- Issued on 2/7/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | KAVIAN REFAHI |
| Green Plans Picked Up | 1/2/2020 | APPLICANT |
| Corrections Issued | 1/15/2020 | KAVIAN REFAHI |
| Quality Review Completed | 1/15/2020 | FELIX FIGUEROA |
| Building Plans Picked Up | 1/15/2020 | APPLICANT |
| Plan Check Approved | 2/7/2020 | KAVIAN REFAHI |
| Issued | 2/7/2020 | LADBS |
| CofO in Progress | 6/15/2021 | KATHRYN BUTTERWORTH |
| Permit Finaled | 6/24/2021 | DEROLD HAUFF |
| CofO Issued | 6/24/2021 | DEROLD HAUFF |
| Permit Finaled | 6/24/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/15/2020 | SARAH GOLDMAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 1/15/2020 | DINAH GARIN |
| Sewer availability | Cleared | 1/15/2020 | DINAH GARIN |
| ZI | Cleared | 1/15/2020 | SARAH GOLDMAN |
| HPOZ | Cleared | 1/16/2020 | KATIE DEBIASE |
| Miscellaneous | Cleared | 1/16/2020 | KATIE DEBIASE |
| Miscellaneous | Cleared | 1/16/2020 | KATIE DEBIASE |
| Green Code | Cleared | 1/28/2020 | RICHARD GARCIA |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 5919 S CROSFT AVENUE LOS ANGELES, CA 90056 |
| Contractor | Owner-Builder | , |
| Engineer | Kang,, Danniel; Lic. No.: S6242 | 633 E 223RD ST B CARSON, CA 90745 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/2/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 4/14/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 4/14/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 4/14/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 4/14/2020 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 4/14/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 4/16/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 4/16/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 4/21/2020 | Corrections Issued | THOMAS LOGRASSO |
| Special/Order Compliance | 5/1/2020 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/4/2020 | Approved | THOMAS LOGRASSO |
| Final | 7/1/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 7/1/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Final | 7/1/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 7/1/2020 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 7/1/2020 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 7/1/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 7/6/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Final | 7/20/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 7/20/2020 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 7/20/2020 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 7/20/2020 | Approved | KATHRYN BUTTERWORTH |
| Final | 12/7/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 4/20/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 6/15/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |