2743 S COLBY AVE 90064
Certificate Information: 2743 S COLBY AVE 90064
- Application / Permit
- 19014-30000-06638
- Plan Check / Job No.
- B19WL06781
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL, FIRST FLOOR ADDITION, AND (N) SECOND STORY ADDITION TO (E) 1-STORY
- Permit Issued
- Issued on 12/7/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2019 | KAVIAN REFAHI |
| Corrections Issued | 1/13/2020 | KAVIAN REFAHI |
| Green Plans Picked Up | 1/17/2020 | APPLICANT |
| Quality Review Completed | 1/23/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 8/31/2020 | KAVIAN REFAHI |
| Issued | 12/7/2020 | APPLICANT |
| Building Plans Picked Up | 12/7/2020 | APPLICANT |
| CofO in Progress | 12/20/2021 | JOHNNY MIRANDA |
| Permit Finaled | 12/30/2021 | KENNETH NAGLE |
| CofO Issued | 12/30/2021 | KENNETH NAGLE |
| Permit Finaled | 12/30/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/6/2020 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2020 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 8/11/2020 | TRACY TATE |
| Sewer availability | Cleared | 8/11/2020 | TRACY TATE |
| Green Code | Cleared | 8/21/2020 | RICHARD GARCIA |
Contact Information
| Contractor | Waconah Construction; Lic. No.: 908219-B | 2431 1/2 ABBOT KINNEY BLVD VENICE, CA 90291 |
| Engineer | Yu,, Irene Gailen; Lic. No.: C68382 | 3411 CAROLINE AVE CULVER CITY, CA 90232 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/22/2020 | Corrections Issued | RICHARD ROBLES |
| Excavation/Setback/Form/Re-Bar | 1/13/2021 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 1/13/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Steel/Welding | 1/26/2021 | Conditional Approval | RICHARD ROBLES |
| Insulation | 1/26/2021 | Partial Approval | RICHARD ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2021 | Partial Approval | RICHARD ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2021 | Approved | RICHARD ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/25/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2021 | Partial Approval | KEVIN SARGSYAN |
| Deputy Steel/Welding | 6/4/2021 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 6/10/2021 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 6/10/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 6/10/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 7/6/2021 | Approved | DONALD GALLAGHER |
| Interior/Exterior Lathing | 7/6/2021 | Partial Approval | DONALD GALLAGHER |
| Shower Pan | 7/6/2021 | Approved | DONALD GALLAGHER |
| Wood Frame | 7/6/2021 | Approved | DONALD GALLAGHER |
| Insulation | 7/12/2021 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 8/23/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/23/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/25/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/25/2021 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 10/20/2021 | Approved | KRISTEN CAUSEY |
| Gas Test | 10/21/2021 | Approved | RYAN SALAZAR |
| HVAC-Final | 10/26/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 10/28/2021 | Partial Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 11/1/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 11/5/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 11/10/2021 | Approved | JOHNNY MIRANDA |
| Final | 11/10/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 11/10/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/10/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 11/10/2021 | Approved | JOHNNY MIRANDA |
| Final | 12/15/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 12/20/2021 | OK to Issue CofO | JOHNNY MIRANDA |