1874-1876 N LANSDOWNE AVE 90032

Certificate Information: 1874-1876 N LANSDOWNE AVE 90032

Application / Permit
19014-30000-06563
Plan Check / Job No.
B19WL06717
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) Garage to ADU and addition to ADU per AB 494 and SB 229
Permit Issued
Issued on 7/11/2020
Issuing Office
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 MANUEL GARCIA
Corrections Issued 12/13/2019 MANUEL GARCIA
Applicant returned to address corrections 6/25/2020 ALFREDO JARA
Plan Check Approved 6/29/2020 ALFREDO JARA
Building Plans Picked Up 6/30/2020 APPLICANT
Issued 7/11/2020 APPLICANT
CofO in Progress 1/10/2023 AMY COLIN
CofO Issued 1/18/2023 DEROLD HAUFF
Permit Finaled 1/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/18/2019 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 12/18/2019 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 12/18/2019 HISASHI KOBAYAKAWA
"D" conditions Cleared 6/10/2020 JASON CHAN
"Q" conditions Cleared 6/10/2020 JASON CHAN
Sewer availability Cleared 6/10/2020 THOMAS LANG
ZI Cleared 6/10/2020 JASON CHAN
Grading Pre-Inspection Cleared 6/29/2020 MANUEL GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/9/2020 Corrections Issued CRAIG VAUGHAN
Grading Pre-Inspection 10/9/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 10/9/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 12/4/2020 Partial Approval COREY HUPP
Deputy Other (see comments) 1/11/2021 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 1/11/2021 Approved COREY HUPP
Excavation/Setback/Form/Re-Bar 2/5/2021 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 5/3/2021 Partial Approval OSVALDO PARAMO
Wood Frame 5/3/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Approved COREY HUPP
Insulation 7/22/2021 Not Ready for Inspection COREY HUPP
Interior/Exterior Lathing 7/22/2021 Not Ready for Inspection COREY HUPP
Green Building Rough 7/26/2021 Approved COREY HUPP
Insulation 7/26/2021 Approved COREY HUPP
Interior/Exterior Lathing 7/26/2021 Partial Approval COREY HUPP
Drywall Nailing 8/12/2021 Approved COREY HUPP
Shower Pan 8/23/2021 Approved COREY HUPP
Interior/Exterior Lathing 8/30/2021 Approved SCOTT FINNILA
BUILDING-Rough-Frame 10/28/2022 Approved AMY COLIN
Final 10/28/2022 Partial Inspection AMY COLIN
Green Building Final 10/28/2022 Approved AMY COLIN
MERV13>=Final 10/28/2022 Approved AMY COLIN
MERV13>=Rough 10/28/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 10/28/2022 SGSOV Approved AMY COLIN
Smoke Detectors 10/28/2022 Approved AMY COLIN
Final 1/10/2023 OK to Issue CofO AMY COLIN