4536 N GRIMES PL 91316
Certificate Information: 4536 N GRIMES PL 91316
- Application / Permit
- 19014-30000-06547
- Plan Check / Job No.
- B19WL06703
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition to existing 2-story SFD
- Permit Issued
- Issued on 7/31/2020
- Issuing Office
- Current Status
- CofO Issued on 8/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | TARIK SAOUD |
| Corrections Issued | 12/17/2019 | TARIK SAOUD |
| Quality Review Completed | 1/2/2020 | FELIX FIGUEROA |
| Green Plans Picked Up | 1/7/2020 | APPLICANT |
| Plan Check Approved | 2/7/2020 | TARIK SAOUD |
| Issued | 7/31/2020 | APPLICANT |
| Building Plans Picked Up | 8/3/2020 | APPLICANT |
| CofO in Progress | 7/19/2022 | JUSTIN HAWLEY |
| Permit Finaled | 8/9/2022 | JOHN JANSON |
| CofO Issued | 8/9/2022 | JOHN JANSON |
| Permit Finaled | 8/9/2022 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/10/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 1/10/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 1/10/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2020 | DINAH GARIN |
| Sewer availability | Cleared | 1/10/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 1/29/2020 | ORVAL HERNANDEZ-MARCIAL |
| Grading Pre-Inspection | Cleared | 2/3/2020 | TARIK SAOUD |
| Roof/Waste drainage to street | Cleared | 2/3/2020 | ANTHONY MAINEZ |
| Green Code | Cleared | 2/6/2020 | RICHARD GARCIA |
Contact Information
| Contractor | Lotus Builders Inc; Lic. No.: 811366-B | 3239 DERONDA DRIVE LOS ANGELES, CA 90068 |
| Engineer | Mezey,, Steven William; Lic. No.: S2665 | 14017 HARTSOOK ST SHERMAN OAKS, CA 91423 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/26/2020 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/14/2020 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 10/15/2020 | Corrections Issued | HENRY KIM |
| Insulation | 10/19/2020 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 10/19/2020 | Partial Inspection | DAVID SANDOVAL |
| Wood Frame | 10/19/2020 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2020 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2020 | No Access for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 1/22/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 1/22/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 2/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 2/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 2/19/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 2/19/2021 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 3/3/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 3/3/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 4/6/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 4/6/2021 | Approved | DAVID SANDOVAL |
| Insulation | 4/6/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 4/20/2021 | Approved | RONALD COWAN |
| Shower Pan | 4/20/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 4/27/2021 | Approved | DAVID SANDOVAL |
| Gas Test | 7/16/2021 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 7/29/2021 | Not Ready for Inspection | RONALD COWAN |
| Final | 7/29/2021 | Corrections Issued | RONALD COWAN |
| Green Building Final | 7/29/2021 | Not Ready for Inspection | RONALD COWAN |
| HVAC-Final | 7/29/2021 | Approved | RONALD COWAN |
| PLUMBING-Final | 7/29/2021 | Corrections Issued | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 7/29/2021 | SGSOV Not Ready | RONALD COWAN |
| Smoke Detectors | 7/29/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Final | 8/5/2021 | Approved | DAVID SANDOVAL |
| HVAC-Final | 8/5/2021 | Approved | DAVID SANDOVAL |
| Final | 8/20/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 8/20/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 8/20/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Approved | DAVID SANDOVAL |
| Service/Power Release | 8/20/2021 | Approved | DAVID SANDOVAL |
| Final | 7/18/2022 | OK to Issue CofO | JUSTIN HAWLEY |