4161 S SUNNYSIDE AVE 90066

Certificate Information: 4161 S SUNNYSIDE AVE 90066

Application / Permit
19014-30000-06478
Plan Check / Job No.
B19WL06664
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & 2-STORY ADDITION TO (E) 1-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE
Permit Issued
Issued on 2/4/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 REZA HAGHIGHAT
Corrections Issued 12/16/2019 REZA HAGHIGHAT
Quality Review Completed 12/23/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/24/2019 APPLICANT
Green Plans Picked Up 12/24/2019 APPLICANT
Plan Check Approved 1/30/2020 REZA HAGHIGHAT
Issued 2/4/2020 LADBS
CofO in Progress 6/3/2021 PIERRE VEGA
CofO in Progress 6/3/2021 ENRIQUE MIRELES
Permit Finaled 6/4/2021 RONALD MYRICK
CofO Issued 6/4/2021 RONALD MYRICK
Permit Finaled 6/4/2021 RONALD MYRICK

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/21/2020 EMIL KYUPELYAN
Green Code Cleared 1/21/2020 RICHARD GARCIA
Permit Cleared 1/21/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/21/2020 EMIL KYUPELYAN
Low Impact Development Cleared 1/27/2020 ORVAL HERNANDEZ-MARCI
Miscellaneous Cleared 1/30/2020 SARAH GOLDMAN
Roof/Waste drainage to street Cleared 1/30/2020 ANTHONY MAINEZ

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Kook & Associates Construction Inc; Lic. No.: 820560-B 12444 VENTURA BLVD STE 105      STUDIO CITY, CA 91604
Engineer Namdar,, Mansour Tom; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/3/2020 Partial Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 7/2/2020 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 7/7/2020 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 7/9/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 7/21/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 8/20/2020 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Corrections Issued JOHNNY MIRANDA
Deputy Wood Construction 10/15/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 10/15/2020 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/16/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 10/16/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/21/2020 Partial Approval DAVID HEINE
HVAC-Rough 10/21/2020 Approved DAVID HEINE
ELECTRICAL-Rough 11/5/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/5/2020 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 11/5/2020 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/9/2020 Approved ENRIQUE MIRELES
Green Building Rough 11/9/2020 Approved ENRIQUE MIRELES
Insulation 11/12/2020 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/16/2020 Approved ENRIQUE MIRELES
Drywall Nailing 11/23/2020 Approved ENRIQUE MIRELES
Underground Mechanical 1/11/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 2/1/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 2/10/2021 Approved ENRIQUE MIRELES
HVAC-Final 2/16/2021 Approved ENRIQUE MIRELES
Final 2/23/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/23/2021 Approved ENRIQUE MIRELES
Green Building Final 2/23/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 2/23/2021 Approved ENRIQUE MIRELES
Final 5/5/2021 Partial Approval ENRIQUE MIRELES
Final 5/24/2021 Conditional Approval WILLIAM MICHALAK
Service/Power Release 5/26/2021 Approved KENNETH NAGLE
Final 6/3/2021 OK to Issue CofO ENRIQUE MIRELES