10620 W ESTHER AVE 90064

Certificate Information: 10620 W ESTHER AVE 90064

Application / Permit
19014-30000-06469
Plan Check / Job No.
B19WL06651
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-story SFD with attached garage & roof trusses.
Permit Issued
Issued on 3/3/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Green Plans Picked Up 12/4/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 JAHANSHAH POURHASSAN
Corrections Issued 12/17/2019 JAHANSHAH POURHASSAN
Quality Review Completed 12/20/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/23/2019 APPLICANT
Plan Check Approved 3/2/2020 JAHANSHAH POURHASSAN
Issued 3/3/2020 LADBS
CofO in Progress 2/2/2021 KEVIN SARGSYAN
Permit Finaled 3/2/2021 KENNETH NAGLE
CofO Issued 3/2/2021 KENNETH NAGLE
Permit Finaled 3/2/2021 KENNETH NAGLE

Permit Application Clearance Information

Trees in Parkway Cleared 1/17/2020 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 2/11/2020 THOMAS LANG
Low Impact Development Cleared 2/11/2020 MITESH PATEL
Permit Cleared 2/11/2020 THOMAS LANG
Roof/Waste drainage to street Cleared 2/11/2020 THOMAS LANG
Sewer availability Cleared 2/11/2020 THOMAS LANG
Green Code Cleared 2/12/2020 DONALD CRICHLOW

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/30/2020 Partial Approval KEVIN SARGSYAN
Sewer 4/30/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 5/12/2020 No Access for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 5/14/2020 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 5/29/2020 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 6/18/2020 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 6/23/2020 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Rough 7/15/2020 Approved KEVIN SARGSYAN
HVAC-Rough 7/15/2020 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 7/15/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 7/15/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 7/20/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 7/27/2020 Corrections Issued KEVIN SARGSYAN
Green Building Rough 7/27/2020 Approved KEVIN SARGSYAN
HVAC-Rough 7/27/2020 Approved KEVIN SARGSYAN
Shower Pan 7/27/2020 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 7/27/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 7/29/2020 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/29/2020 SGSOV Not Ready KEVIN SARGSYAN
Drywall Nailing 8/13/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 8/24/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 11/12/2020 Corrections Issued KEVIN SARGSYAN
Gas Test 11/12/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 11/12/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Final 1/6/2021 Approved KEVIN SARGSYAN
Final 1/27/2021 Corrections Issued KEVIN SARGSYAN
Green Building Final 1/27/2021 Approved KEVIN SARGSYAN
HVAC-Final 1/27/2021 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/27/2021 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 1/27/2021 Approved KEVIN SARGSYAN
Smoke Detectors 1/27/2021 Approved KEVIN SARGSYAN
Final 2/2/2021 OK to Issue CofO KEVIN SARGSYAN
HVAC-Final 2/2/2021 Approved KEVIN SARGSYAN