3484 S FEDERAL AVE 90066

Certificate Information: 3484 S FEDERAL AVE 90066

Application / Permit
19014-30000-06459
Plan Check / Job No.
B19WL06638
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of a garage and both 1st and 2nd floor addition to existing 1-story single family dwelling
Permit Issued
Issued on 5/14/2021
Issuing Office
Current Status
CofO Issued on 6/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 MARJAN SHENASI
Green Plans Picked Up 1/7/2020 APPLICANT
Corrections Issued 1/8/2020 MARJAN SHENASI
Quality Review Completed 1/16/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/22/2020 MARJAN SHENASI
Applicant returned to address corrections 10/29/2020 MARJAN SHENASI
Plan Check Approved 12/9/2020 MARJAN SHENASI
Building Plans Picked Up 12/9/2020 APPLICANT
Issued 5/14/2021 APPLICANT
CofO in Progress 6/24/2022 KENNETH NAGLE
Permit Finaled 6/29/2022 DANIEL ORRANTE
CofO Issued 6/29/2022 DANIEL ORRANTE
Permit Finaled 6/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/19/2020 MAHELET GEBEYHU
Sewer availability Cleared 3/19/2020 MAHELET GEBEYHU
Specific Plan Cleared 3/31/2020 FREDDY GARCIA
Low Impact Development Cleared 9/24/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 10/14/2020 HISASHI KOBAYAKAWA
GPI Written Notices Cleared 10/22/2020 MARJAN SHENASI
Grading Pre-Inspection Cleared 10/22/2020 MARJAN SHENASI
Green Code Cleared 10/29/2020 DONALD CRICHLOW

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Lightning Construction & Design Inc; Lic. No.: 951122-B 6047 TAMPA AVE #303      TARZANA, CA 91356

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/21/2021 Conditional Approval AMY COLIN
Excavation/Setback/Form/Re-Bar 6/21/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 6/21/2021 Conditional Approval EVAN COOPER
Deputy Reinf. Concrete 6/23/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 6/29/2021 Partial Inspection JUAN VALENZUELA
Green Building Rough 6/29/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 6/29/2021 Corrections Issued JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 7/8/2021 Approved DONALD GALLAGHER
Footing/Foundation/Slab 7/8/2021 Approved DONALD GALLAGHER
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 8/31/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/19/2021 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 10/19/2021 Corrections Issued JOHNNY MIRANDA
Rough-Elec/Plmb/HVAC 10/19/2021 Corrections Issued JOHNNY MIRANDA
Verify Sprinkler Sign Off 10/19/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 10/27/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 10/27/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 10/27/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/27/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 10/27/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 11/1/2021 Approved JOHNNY MIRANDA
Insulation 11/1/2021 Conditional Approval JOHNNY MIRANDA
Interior/Exterior Lathing 11/1/2021 Approved JOHNNY MIRANDA
Drywall Nailing 11/8/2021 Approved JOHNNY MIRANDA
Insulation 11/8/2021 Approved JOHNNY MIRANDA
Shower Pan 11/8/2021 Corrections Issued JOHNNY MIRANDA
Shower Pan 11/10/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 11/16/2021 Approved JOHNNY MIRANDA
Special/Order Compliance 1/26/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 4/14/2022 Approved JOHNNY MIRANDA
Final 6/2/2022 Corrections Issued KENNETH NAGLE
Green Building Final 6/2/2022 Not Ready for Inspection KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Not Ready KENNETH NAGLE
Smoke Detectors 6/2/2022 Approved KENNETH NAGLE
Final 6/7/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 6/7/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/7/2022 SGSOV Not Ready JOHNNY MIRANDA
Service/Power Release 6/7/2022 Approved JOHNNY MIRANDA
Final 6/14/2022 Conditional Approval JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Approved JOHNNY MIRANDA