4030 S MARCASEL AVE 90066

Certificate Information: 4030 S MARCASEL AVE 90066

Application / Permit
19014-30000-06429
Plan Check / Job No.
B19WL06602
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st, 2nd floor and garage addition to (e) 1-story single family dwelling, major remodel
Permit Issued
Issued on 8/13/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 MARJAN SHENASI
Green Plans Picked Up 12/30/2019 APPLICANT
Corrections Issued 1/13/2020 MARJAN SHENASI
Quality Review Completed 1/23/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/11/2020 MARJAN SHENASI
Applicant returned to address corrections 7/2/2020 MARJAN SHENASI
Plan Check Approved 7/28/2020 MARJAN SHENASI
Building Plans Picked Up 7/29/2020 APPLICANT
Issued 8/13/2020 APPLICANT
CofO in Progress 8/11/2022 JESUS RODRIGUEZ
Permit Finaled 8/17/2022 DANIEL ORRANTE
CofO Issued 8/17/2022 DANIEL ORRANTE
Permit Finaled 8/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 3/11/2020 ORVAL HERNANDEZ-MARCIAL
Green Code Cleared 4/17/2020 RICHARD GARCIA
Hydrant and Access approval Cleared 5/1/2020 GEORGE SUCHAND
Permit Cleared 5/7/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/8/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 5/8/2020 DINAH GARIN
Sewer availability Cleared 5/8/2020 DINAH GARIN
ZA Case Cleared 5/11/2020 JASON CHAN
Specific Plan Cleared 5/14/2020 VALERIA CEJA
Trees in Parkway Cleared 6/2/2020 JOHN KIM

Contact Information

Contractor Yd Construction & Development Inc; Lic. No.: 839200-B 15030 VENTURA BLVD #216      SHERMAN OAKS, CA 91403
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/27/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 10/28/2020 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 10/29/2020 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 11/5/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 11/9/2020 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 11/20/2020 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 12/2/2020 Partial Approval ENRIQUE MIRELES
Deputy Drilled-In Anchors 12/4/2020 Conditional Approval JOHNNY MIRANDA
Deputy Steel/Welding 12/4/2020 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/10/2020 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/22/2020 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 12/28/2020 Approved ENRIQUE MIRELES
Reinforced Concrete Frame 1/8/2021 Approved ENRIQUE MIRELES
HVAC-Rough 2/10/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/10/2021 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 3/17/2021 Approved ENRIQUE MIRELES
HVAC-Rough 3/17/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/17/2021 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 3/17/2021 Approved ENRIQUE MIRELES
Wood Frame 3/17/2021 Approved ENRIQUE MIRELES
Insulation 3/23/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/23/2021 Not Ready for Inspection ENRIQUE MIRELES
Sewer 3/23/2021 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 3/23/2021 Not Ready for Inspection ENRIQUE MIRELES
Drywall Nailing 3/30/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/30/2021 Approved ENRIQUE MIRELES
Shower Pan 3/30/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/15/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 10/29/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 10/29/2021 Approved ENRIQUE MIRELES
Final 10/29/2021 Not Ready for Inspection ENRIQUE MIRELES
Green Building Final 10/29/2021 Approved ENRIQUE MIRELES
Green Building Rough 10/29/2021 Approved ENRIQUE MIRELES
HVAC-Final 10/29/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 10/29/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 10/29/2021 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 10/29/2021 Approved ENRIQUE MIRELES
Final 5/3/2022 Corrections Issued PATRICK QUALEY
Final 7/28/2022 Corrections Issued STEPHANIE SWANSON
Final 8/10/2022 OK to Issue CofO JESUS RODRIGUEZ