5353 S 9TH AVE 90043
Certificate Information: 5353 S 9TH AVE 90043
- Application / Permit
- 19014-30000-06423
- Plan Check / Job No.
- B19WL06598
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION AND AN ADDITTION OF (E) DETACHED 2-CAR GARAGE INTO AN ADU UNIT AS PER AB 494 & SB229
- Permit Issued
- Issued on 5/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 12/24/2019 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 1/10/2020 | TARIK SAOUD |
| Green Plans Picked Up | 1/10/2020 | APPLICANT |
| Applicant returned to address corrections | 7/22/2020 | VLADIMIR ARUTYUNYAN |
| Plan Check Approved | 10/9/2020 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 10/9/2020 | APPLICANT |
| Issued | 5/21/2021 | APPLICANT |
| CofO in Progress | 5/18/2023 | ANTHONY EGSON |
| CofO in Progress | 5/30/2023 | ANTHONY EGSON |
| CofO in Progress | 6/8/2023 | ANTHONY EGSON |
| Permit Finaled | 6/29/2023 | DEROLD HAUFF |
| CofO Issued | 6/29/2023 | DEROLD HAUFF |
| Permit Finaled | 6/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 2/28/2020 | DINAH GARIN |
| Sewer availability | Cleared | 2/28/2020 | DINAH GARIN |
| Green Code | Cleared | 3/18/2020 | DONALD CRICHLOW |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pouraghabagher,, Ali; Lic. No.: C56013 | PO BOX 244 WOODLAND HILLS, CA 91365 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/10/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 8/17/2021 | Partial Approval | DAVID FEILER |
| Sewer | 8/17/2021 | Approved | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 8/27/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/27/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 9/2/2021 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 9/2/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 12/2/2021 | Corrections Issued | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 2/4/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 2/4/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/28/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 2/28/2022 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 3/4/2022 | No Access for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 3/14/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 3/14/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/12/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/12/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/12/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 5/12/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/26/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/26/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 5/26/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 5/26/2022 | Approved | ANTHONY EGSON |
| Insulation | 6/9/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/9/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/28/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 7/13/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/14/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 11/14/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 11/14/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 11/14/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 11/14/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 11/14/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 11/14/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Not Required | ANTHONY EGSON |
| Smoke Detectors | 11/14/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/30/2022 | Approved | ANTHONY EGSON |
| Final | 12/30/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 12/30/2022 | Approved | ANTHONY EGSON |
| Service/Power Release | 1/11/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 1/23/2023 | Approved | ANTHONY EGSON |
| Final | 5/18/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 5/30/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 6/7/2023 | OK to Issue CofO | ANTHONY EGSON |