705-707 E PALMS BLVD 90291

Certificate Information: 705-707 E PALMS BLVD 90291

Application / Permit
19014-30000-06391
Plan Check / Job No.
B19WL06573
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Enclose 1st floor patio and addition on 2nd floor to existing duplex. Interior remodel through out both floors.
Permit Issued
Issued on 5/13/2021
Issuing Office
Current Status
CofO Issued on 6/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Green Plans Picked Up 1/2/2019 APPLICANT
Submitted 11/22/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 MANUEL GARCIA
Corrections Issued 12/17/2019 MANUEL GARCIA
Quality Review Completed 12/26/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/16/2020 MANUEL GARCIA
Applicant returned to address corrections 3/27/2020 MANUEL GARCIA
Applicant returned to address corrections 5/14/2020 MANUEL GARCIA
Plan Check Approved 10/16/2020 MANUEL GARCIA
Issued 5/13/2021 APPLICANT
Building Plans Picked Up 5/20/2021 APPLICANT
CofO in Progress 6/5/2025 JESUS RODRIGUEZ
Permit Finaled 6/7/2025 RICHARD STEINBACH
CofO Issued 6/7/2025 RICHARD STEINBACH
Permit Finaled 6/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/16/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/16/2020 DINAH GARIN
Sewer availability Cleared 1/16/2020 DINAH GARIN
Miscellaneous Cleared 1/23/2020 SARAH GOLDMAN
Miscellaneous Cleared 1/23/2020 SARAH GOLDMAN
Tenant Habitability Plan Cleared 2/20/2020 MICHAEL GREGERSON
Specific Plan Cleared 2/25/2020 JEFF KHAU
Coastal Zone Cleared 3/31/2020 MARITZA PRZEKOP
Green Code Cleared 4/8/2020 DONALD CRICHLOW
Low Impact Development Cleared 8/18/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 8/25/2020 DINAH GARIN

Contact Information

Architect Rechtszajd,, Daniela; Lic. No.: C31333 5410 VILLAGE GREEN      LOS ANGELES, CA 90016
Contractor Celtic Design And Construction; Lic. No.: 778960-B 2633 LINCOLN BLVD #304      SANTA MONICA, CA 90405
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/3/2023 Not Ready for Inspection HERBERT GIRON
Pre-Inspection 4/12/2023 Corrections Issued EVAN COOPER
Excavation/Setback/Form/Re-Bar 5/17/2023 Partial Approval EVAN COOPER
Footing/Foundation/Slab 5/17/2023 Partial Approval EVAN COOPER
Footing/Foundation/Slab 6/15/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 10/23/2023 Approved HERBERT GIRON
Wood Frame 10/23/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 1/11/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 1/23/2024 Approved HERBERT GIRON
PLUMBING-Rough 1/23/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 1/31/2024 Corrections Issued HERBERT GIRON
Pre-Inspection 2/7/2024 Partial Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Approved HERBERT GIRON
PLUMBING-Rough 2/15/2024 Corrections Issued HERBERT GIRON
PLUMBING-Rough 2/16/2024 Not Ready for Inspection HERBERT GIRON
Service/Power Release 2/26/2024 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 3/1/2024 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 3/1/2024 Partial Approval HERBERT GIRON
PLUMBING-Rough 3/1/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/6/2024 Not Ready for Inspection HERBERT GIRON
Green Building Rough 3/6/2024 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 3/6/2024 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 3/8/2024 Partial Approval HERBERT GIRON
Green Building Rough 3/8/2024 Approved HERBERT GIRON
HVAC-Rough 3/8/2024 Conditional Approval HERBERT GIRON
Verify Sprinkler Sign Off 3/8/2024 Approved HERBERT GIRON
Insulation 3/22/2024 Approved HERBERT GIRON
Shower Pan 3/22/2024 Approved HERBERT GIRON
Light Gage Steel Frame 3/28/2024 Approved HERBERT GIRON
Drywall Nailing 4/4/2024 Partial Approval HERBERT GIRON
Drywall Nailing 4/11/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 4/16/2024 Approved HERBERT GIRON
ELECTRICAL-Final 12/10/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 12/10/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 12/13/2024 Not Ready for Inspection JESUS PINEDA
Gas Test 12/13/2024 Approved JESUS PINEDA
PLUMBING-Final 12/13/2024 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 12/19/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 1/15/2025 Approved EVAN COOPER
PLUMBING-Final 1/15/2025 Approved EVAN COOPER
Service/Power Release 1/15/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 2/21/2025 Not Ready for Inspection HERBERT GIRON
Final 2/21/2025 Not Ready for Inspection HERBERT GIRON
Green Building Final 2/21/2025 Not Ready for Inspection HERBERT GIRON
HVAC-Final 2/21/2025 Not Ready for Inspection HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 2/21/2025 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 6/4/2025 Approved JESUS RODRIGUEZ
Final 6/4/2025 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 6/4/2025 Approved JESUS RODRIGUEZ
HVAC-Final 6/4/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 6/4/2025 Approved JESUS RODRIGUEZ