3332 W CASITAS AVE 90039

Certificate Information: 3332 W CASITAS AVE 90039

Application / Permit
19014-30000-06364
Plan Check / Job No.
B19WL06542
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition of ADU to (e) detached garage at rear of property per AB 494 & SB 229. Construction per WFPP
Permit Issued
Issued on 2/9/2021
Issuing Office
Current Status
CofO Issued on 4/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 KAVIAN REFAHI
Corrections Issued 11/26/2019 KAVIAN REFAHI
Applicant returned to address corrections 9/8/2020 KAVIAN REFAHI
Plan Check Approved 10/5/2020 KAVIAN REFAHI
Building Plans Picked Up 10/6/2020 APPLICANT
Issued 2/9/2021 APPLICANT
CofO in Progress 4/5/2022 HAMIK HARTOUNIAN
Permit Finaled 4/25/2022 DEROLD HAUFF
CofO Issued 4/25/2022 DEROLD HAUFF
Permit Finaled 4/25/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/9/2019 ANTHONY MAINEZ
Low Impact Development Cleared 12/20/2019 ORVAL HERNANDEZ-MARCIAL
ZI Cleared 12/30/2019 DENZEL HENDERSON
Construction near power lines Cleared 3/6/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/17/2020 THOMAS LANG
Sewer availability Cleared 8/17/2020 THOMAS LANG
Roof/Waste drainage to street Cleared 9/25/2020 THOMAS LANG

Contact Information

No Data Available.

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/17/2021 Approved HAMIK HARTOUNIAN
Underground Mechanical 2/17/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/25/2021 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/25/2021 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/25/2021 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 2/25/2021 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 2/25/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 2/25/2021 Approved HAMIK HARTOUNIAN
Gas Test 3/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Sewer 3/1/2021 Approved HAMIK HARTOUNIAN
Insulation 3/4/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2021 Partial Approval HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 3/8/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/10/2021 Approved JOSEPH MCGARRY
Green Building Rough 3/10/2021 Approved JOSEPH MCGARRY
Insulation 3/10/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 3/10/2021 Partial Approval JOSEPH MCGARRY
Drywall Nailing 3/12/2021 Approved SCOTT FINNILA
Interior/Exterior Lathing 3/12/2021 Partial Approval SCOTT FINNILA
Pre-Inspection 4/8/2021 Corrections Issued HAMIK HARTOUNIAN
Gas Test 5/19/2021 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 6/14/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Final 10/25/2021 Not Ready for Inspection ADAM ESCOTO
Gas Test 10/25/2021 Approved ADAM ESCOTO
Green Building Final 10/25/2021 Approved ADAM ESCOTO
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Not Ready ADAM ESCOTO
Smoke Detectors 10/25/2021 Corrections Issued ADAM ESCOTO
Final 1/13/2022 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 1/13/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 1/13/2022 Not Ready for Inspection OSVALDO PARAMO
Final 2/24/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Smoke Detectors 2/24/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Final 3/18/2022 Partial Approval HAMIK HARTOUNIAN
Smoke Detectors 3/18/2022 Approved HAMIK HARTOUNIAN
Final 3/29/2022 Corrections Issued HAMIK HARTOUNIAN
Final 4/5/2022 OK to Issue CofO HAMIK HARTOUNIAN