3334 S CLUB DR 90064
Certificate Information: 3334 S CLUB DR 90064
- Application / Permit
- 19014-30000-06352
- Plan Check / Job No.
- B19WL06530
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Two-story addition to an (E) one-story SFD leaving 2' portion of footing &wall.
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/21/2019 | APPLICANT |
| Green Plans Picked Up | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | JAHANSHAH POURHASSAN |
| Corrections Issued | 12/11/2019 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 12/20/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/23/2019 | APPLICANT |
| Plan Check Approved | 1/6/2020 | JAHANSHAH POURHASSAN |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 6/14/2021 | KEVIN SARGSYAN |
| Permit Finaled | 7/1/2021 | KENNETH NAGLE |
| CofO Issued | 7/1/2021 | KENNETH NAGLE |
| Permit Finaled | 7/1/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Green Code | Cleared | 12/27/2019 | DONALD CRICHLOW |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 12/30/2019 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 12/30/2019 | ANDRES COVARRUBIAS |
| Permit | Cleared | 12/30/2019 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 12/30/2019 | ERIK BEASLEY |
| GPI Written Notices | Cleared | 1/6/2020 | JAHANSHAH POURHASSAN |
| Grading Pre-Inspection | Cleared | 1/6/2020 | JAHANSHAH POURHASSAN |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Bookie Development Inc; Lic. No.: 977585-B | 10509 CLARKSON ROAD LOS ANGELES, CA 90064 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/17/2020 | Approved | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 2/5/2020 | Partial Approval | RONALD WEBER |
| Footing/Foundation/Slab | 2/24/2020 | Approved | RONALD WEBER |
| Underground Mechanical | 2/24/2020 | Partial Approval | RONALD WEBER |
| Deputy Wood Construction | 3/25/2020 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2020 | Partial Approval | JOHNNY MIRANDA |
| Gas Test | 6/26/2020 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/26/2020 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/6/2020 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 7/6/2020 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Wood Construction | 7/7/2020 | Conditional Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/9/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2020 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 7/9/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 7/9/2020 | Corrections Issued | KEVIN SARGSYAN |
| MERV13>=Rough | 7/9/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Wood Frame | 7/9/2020 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/17/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 7/17/2020 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 7/17/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 7/17/2020 | Approved | KEVIN SARGSYAN |
| MERV13>=Rough | 7/17/2020 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/21/2020 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 7/21/2020 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 7/21/2020 | Approved | KEVIN SARGSYAN |
| Insulation | 7/27/2020 | Approved | KEVIN SARGSYAN |
| Shower Pan | 7/30/2020 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 7/31/2020 | Conditional Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 8/11/2020 | Approved | KEVIN SARGSYAN |
| Pre-Inspection | 11/16/2020 | Approved | KEVIN SARGSYAN |
| HVAC-Final | 3/1/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 3/17/2021 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 3/18/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 3/18/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 3/22/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 3/26/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 4/13/2021 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 5/7/2021 | Approved | KEVIN SARGSYAN |
| Final | 5/7/2021 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 5/7/2021 | Approved | KEVIN SARGSYAN |
| MERV13>=Final | 5/7/2021 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/7/2021 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 5/7/2021 | Approved | KEVIN SARGSYAN |
| Final | 5/28/2021 | Not Ready for Inspection | EVAN COOPER |
| Final | 6/14/2021 | OK to Issue CofO | KEVIN SARGSYAN |
| Service/Power Release | 6/18/2021 | Approved | KEVIN SARGSYAN |