2923 S CARDIFF AVE 90034

Certificate Information: 2923 S CARDIFF AVE 90034

Application / Permit
19014-30000-06275
Plan Check / Job No.
B19WL06454
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel and addition to (e) SFD. New studs and roof. Wall on south to remain.
Permit Issued
Issued on 3/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2019 APPLICANT
Application Withdrawn 11/19/2019 APPLICANT
Re-Activate Applicaton 11/19/2019 APPLICANT
Assigned to Plan Check Engineer 11/27/2019 SAMUEL GONZALEZ
Green Plans Picked Up 11/27/2019 APPLICANT
Corrections Issued 12/3/2019 SAMUEL GONZALEZ
Quality Review Completed 12/12/2019 LAWRENCE QUIRANTE
Plan Check Approved 2/14/2020 SAMUEL GONZALEZ
Issued 3/10/2020 LADBS
Building Plans Picked Up 5/8/2020 APPLICANT
CofO in Progress 6/24/2022 KEVIN SARGSYAN
Permit Finaled 6/27/2022 DANIEL ORRANTE
CofO Issued 6/27/2022 DANIEL ORRANTE
Permit Finaled 6/27/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 1/14/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 1/14/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/16/2020 JEANIE LAM
Green Code Cleared 1/17/2020 COLIN LOREDO
Grading Pre-Inspection Cleared 2/14/2020 SAMUEL GONZALEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mercado,, Lizandro; Lic. No.: S4331 25583 AVENUE STANFORD      VALENCIA, CA 91355

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/30/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 5/14/2020 Corrections Issued KEVIN SARGSYAN
Green Building Rough 5/14/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 5/14/2020 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 5/22/2020 Partial Approval KEVIN SARGSYAN
Green Building Rough 5/22/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 5/22/2020 Partial Approval KEVIN SARGSYAN
Insulation 5/29/2020 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 5/29/2020 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 6/2/2020 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/2/2020 Partial Approval KEVIN SARGSYAN
Green Building Rough 6/2/2020 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/24/2020 Partial Approval KEVIN SARGSYAN
HVAC-Rough 8/11/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 10/14/2020 Approved EVAN COOPER
Sewer 10/14/2020 Approved EVAN COOPER
ELECTRICAL-Rough 1/5/2021 Approved KENNETH NAGLE
ELECTRICAL-Rough 1/7/2021 Approved KENNETH NAGLE
BUILDING-Rough-Frame 1/21/2021 Corrections Issued KENNETH NAGLE
Green Building Rough 1/21/2021 Not Ready for Inspection KENNETH NAGLE
Insulation 2/25/2021 Approved EVAN COOPER
Drywall Nailing 6/1/2021 Approved EVAN COOPER
Interior/Exterior Lathing 6/1/2021 Approved EVAN COOPER
Shower Pan 6/1/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 12/10/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/10/2021 Approved OGANES TARAKHCHYAN
Final 12/10/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 12/10/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 12/10/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 12/10/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Final 12/10/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/10/2021 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 12/10/2021 Approved OGANES TARAKHCHYAN
Smoke Detectors 12/10/2021 Approved OGANES TARAKHCHYAN
Final 6/8/2022 Corrections Issued KEVIN SARGSYAN
Final 6/24/2022 Conditional Approval KEVIN SARGSYAN