5824 N SATSUMA AVE 91601
Certificate Information: 5824 N SATSUMA AVE 91601
- Application / Permit
- 19014-30000-06254
- Plan Check / Job No.
- B19WL06439
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 260 SF ADDITION TO SFD. ADDITION WILL INCLUDE A (N) BATHROOM AND REPLCAMENT OF AND (E) BEDROOM
- Permit Issued
- Issued on 11/30/2020
- Issuing Office
- Current Status
- CofO Issued on 8/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | SERGIO SILVA |
| Corrections Issued | 11/25/2019 | SERGIO SILVA |
| Building Plans Picked Up | 12/2/2019 | APPLICANT |
| Plan Check Approved | 12/6/2019 | SERGIO SILVA |
| Issued | 11/30/2020 | APPLICANT |
| CofO in Progress | 8/30/2022 | JOHN HAYES |
| Permit Finaled | 8/30/2022 | MICHAEL SMITH |
| CofO Issued | 8/30/2022 | MICHAEL SMITH |
| Permit Finaled | 8/30/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| CPC | Cleared | 12/3/2019 | ANNA VAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | THOMAS LANG |
| Permit | Cleared | 12/3/2019 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 12/3/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/3/2019 | THOMAS LANG |
| Hold | Cleared | 12/16/2020 | JEREMY CORONEL |
Contact Information
| Architect | Asamoah,, B Kwesi; Lic. No.: C36558 | 850 ROSE AVENUE VENICE, CA 90291 |
| Contractor | C B L Construction Inc; Lic. No.: 1061485-B | 8309 LAUREL CYN BLVD #238 SUN VALLEY, CA 91352 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/18/2020 | No Access for Inspection | DANIEL DREW |
| Drywall Nailing | 12/18/2020 | Not Ready for Inspection | DANIEL DREW |
| Footing/Foundation/Slab | 12/18/2020 | No Access for Inspection | DANIEL DREW |
| Green Building Final | 12/18/2020 | No Access for Inspection | DANIEL DREW |
| Green Building Rough | 12/18/2020 | No Access for Inspection | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 12/18/2020 | SGSOV Not Ready | DANIEL DREW |
| Smoke Detectors | 12/18/2020 | No Access for Inspection | DANIEL DREW |
| Footing/Foundation/Slab | 12/22/2020 | Corrections Issued | DANIEL DREW |
| Excavation/Setback/Form/Re-Bar | 12/23/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 1/13/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 1/13/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 1/26/2021 | Partial Approval | DANIEL DREW |
| HVAC-Rough | 1/26/2021 | Partial Approval | DANIEL DREW |
| PLUMBING-Rough | 1/26/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 2/16/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 2/16/2021 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 2/16/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Rough | 2/26/2021 | Approved | DANIEL DREW |
| Insulation | 3/16/2021 | Not Ready for Inspection | DANIEL DREW |
| Interior/Exterior Lathing | 3/16/2021 | Not Ready for Inspection | DANIEL DREW |
| Insulation | 3/25/2021 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 3/25/2021 | Approved | DANIEL DREW |
| Drywall Nailing | 4/13/2021 | Approved | DANIEL DREW |
| Green Building Rough | 4/13/2021 | Approved | DANIEL DREW |
| Service/Power Release | 6/3/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/29/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 6/29/2021 | SGSOV Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 8/31/2021 | No Access for Inspection | DANIEL DREW |
| Final | 8/31/2021 | No Access for Inspection | DANIEL DREW |
| Footing/Foundation/Slab | 8/31/2021 | No Access for Inspection | DANIEL DREW |
| Green Building Final | 8/31/2021 | No Access for Inspection | DANIEL DREW |
| Smoke Detectors | 8/31/2021 | No Access for Inspection | DANIEL DREW |
| BUILDING-Rough-Frame | 9/15/2021 | Approved | DANIEL DREW |
| Final | 9/15/2021 | Corrections Issued | DANIEL DREW |
| Footing/Foundation/Slab | 9/15/2021 | Approved | DANIEL DREW |
| Green Building Final | 9/15/2021 | Not Ready for Inspection | DANIEL DREW |
| Smoke Detectors | 9/15/2021 | Approved | DANIEL DREW |
| Final | 11/19/2021 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 11/19/2021 | Approved | ARAM AVEDISIAN |
| Final | 2/22/2022 | Corrections Issued | THOMAS FINNILA |
| Final | 6/28/2022 | OK to Issue CofO | JOHN HAYES |