12116 W SARDIS AVE 90064
Certificate Information: 12116 W SARDIS AVE 90064
- Application / Permit
- 19014-30000-06236
- Plan Check / Job No.
- B19WL06420
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel & 1-story addition to (e) 1-story single family dwelling 2/ att. 1-car garage
- Permit Issued
- Issued on 2/14/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | REZA HAGHIGHAT |
| Corrections Issued | 12/2/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 12/13/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/16/2019 | APPLICANT |
| Green Plans Picked Up | 12/16/2019 | APPLICANT |
| Plan Check Approved | 2/7/2020 | REZA HAGHIGHAT |
| Issued | 2/14/2020 | LADBS |
| CofO in Progress | 7/22/2022 | JOHNNY MIRANDA |
| CofO in Progress | 7/25/2022 | JOHNNY MIRANDA |
| Permit Finaled | 8/2/2022 | DANIEL ORRANTE |
| CofO Issued | 8/2/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/2/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2020 | JUAN ASHTON |
| Low Impact Development | Cleared | 1/22/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/22/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 1/22/2020 | JUAN ASHTON |
| Green Code | Cleared | 2/11/2020 | RICHARD GARCIA |
Contact Information
| Architect | Hamilton,, Peter W; Lic. No.: C37714 | 1444 COLBY AVENUE #1 LOS ANGELES, CA 90025 |
| Contractor | Globus Builder Inc; Lic. No.: 961380-B | 6350 LAUREL CANYON BLVD SUITE 400 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Lau,, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 3/9/2020 | Approved | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 3/9/2020 | Not Ready for Inspection | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 3/16/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 3/18/2020 | Corrections Issued | KENNETH NAGLE |
| Footing/Foundation/Slab | 3/25/2020 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Insulation | 4/7/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/7/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2020 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 4/14/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/14/2020 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2020 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 4/17/2020 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/8/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 5/8/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/8/2020 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/8/2020 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/12/2020 | Corrections Issued | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2020 | Corrections Issued | KENNETH NAGLE |
| Green Building Rough | 5/12/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Interior/Exterior Lathing | 5/21/2020 | Corrections Issued | KENNETH NAGLE |
| Service/Power Release | 5/21/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Shower Pan | 5/21/2020 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 5/29/2020 | No Access for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/3/2020 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/8/2020 | Corrections Issued | KENNETH NAGLE |
| ELECTRICAL-Rough | 6/8/2020 | Approved | KENNETH NAGLE |
| Green Building Rough | 6/8/2020 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 6/8/2020 | Not Ready for Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/12/2020 | Approved | EVAN COOPER |
| Green Building Rough | 6/12/2020 | Approved | EVAN COOPER |
| Insulation | 6/12/2020 | Corrections Issued | EVAN COOPER |
| Insulation | 6/15/2020 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/15/2020 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 6/19/2020 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2020 | SGSOV Not Ready | EVAN COOPER |
| Final | 8/26/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/31/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 8/31/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/31/2020 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 8/31/2020 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/31/2020 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/31/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 9/3/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/24/2020 | SGSOV Not Ready | RICHARD ROBLES |
| BUILDING-Rough-Frame | 11/9/2021 | Approved | JOHNNY MIRANDA |
| Final | 11/9/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Final | 7/13/2022 | Conditional Approval | JOHNNY MIRANDA |
| Final | 7/22/2022 | OK to Issue CofO | JOHNNY MIRANDA |