2746-2748 N BELDEN DR 90068
Certificate Information: 2746-2748 N BELDEN DR 90068
- Application / Permit
- 19014-30000-06208
- Plan Check / Job No.
- B19WL06401
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Garage with ADU above addition to (E) SFD per AB 494 & SB229.
- Permit Issued
- Issued on 9/29/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 12/17/2019 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 12/27/2019 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 1/2/2020 | APPLICANT |
| Applicant returned to address corrections | 8/19/2020 | VLADIMIR ARUTYUNYAN |
| Plan Check Approved | 9/6/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 9/29/2020 | APPLICANT |
| Building Plans Picked Up | 9/30/2020 | APPLICANT |
| CofO in Progress | 10/7/2021 | BRIAN SULLIVAN |
| Permit Finaled | 6/18/2022 | DEROLD HAUFF |
| CofO Issued | 6/18/2022 | DEROLD HAUFF |
| Permit Finaled | 6/18/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/13/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 2/13/2020 | DINAH GARIN |
| Sewer availability | Cleared | 2/13/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 2/25/2020 | DOMINIQUE MEDINA |
| Green Code | Cleared | 2/27/2020 | DONALD CRICHLOW |
| ZA Case | Cleared | 2/27/2020 | LOUIS ORTEGA |
| Specific Plan | Cleared | 5/11/2020 | LIKYELESH ABERA |
| Grading Pre-Inspection | Cleared | 9/4/2020 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Rocka Builders Inc; Lic. No.: 1050219-B | 3719 VERDUGO RD LOS ANGELES, CA 90065 |
| Engineer | Behshid,, Farshid; Lic. No.: S4585 | 4647 ENCINAS DR LA CANADA, CA 91011 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/16/2020 | Partial Inspection | BRIAN SULLIVAN |
| Pre-Inspection | 12/4/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 12/22/2020 | Corrections Issued | RAUL BARAJAS |
| Piling/Pier/Caisson | 12/30/2020 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/14/2021 | Corrections Issued | BRIAN SULLIVAN |
| Underground Mechanical | 1/14/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 1/28/2021 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2021 | Partial Approval | BRIAN SULLIVAN |
| Wood Frame | 3/2/2021 | Partial Approval | BRIAN SULLIVAN |
| Special/Order Compliance | 3/10/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Special/Order Compliance | 3/15/2021 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2021 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/21/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 4/21/2021 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 4/21/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 5/3/2021 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/5/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/5/2021 | Partial Approval | BRIAN SULLIVAN |
| Drywall Nailing | 6/11/2021 | Partial Inspection | THOMAS LOGRASSO |
| Sewer | 6/24/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Sewer | 7/1/2021 | Approved | BRIAN SULLIVAN |
| Sewer | 7/6/2021 | Approved | BRIAN SULLIVAN |
| Underground Mechanical | 7/21/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/5/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 8/5/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 8/5/2021 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 8/5/2021 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 8/5/2021 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 8/5/2021 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 8/5/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 8/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Final | 8/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 8/9/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Final | 10/6/2021 | Approved | BRIAN SULLIVAN |
| Final | 10/6/2021 | OK to Issue CofO | BRIAN SULLIVAN |
| Green Building Final | 10/6/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 10/6/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 10/6/2021 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 10/6/2021 | Approved | BRIAN SULLIVAN |