1623 S MANSFIELD AVE 90019

Certificate Information: 1623 S MANSFIELD AVE 90019

Application / Permit
19014-30000-06200
Plan Check / Job No.
B19WL06391
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st & 2nd story addition with attached 2 car garage to (E) 1 story SFD.
Permit Issued
Issued on 1/17/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2019 APPLICANT
Green Plans Picked Up 11/21/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 12/2/2019 VLADIMIR ARUTYUNYAN
Quality Review Completed 12/12/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/13/2019 APPLICANT
Plan Check Approved 1/17/2020 VLADIMIR ARUTYUNYAN
Issued 1/17/2020 LADBS
CofO in Progress 12/15/2020 DAVID CHAN
Permit Finaled 2/17/2023 DANIEL ORRANTE
CofO Issued 2/17/2023 DANIEL ORRANTE
Permit Finaled 2/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Trees in Parkway Cleared 12/21/2019 JOHN KIM
Green Code Cleared 1/9/2020 DONALD CRICHLOW
Eng Process Fee Ord 176,300 Cleared 1/14/2020 LEE GUILBEAUX
Low Impact Development Cleared 1/14/2020 SARAH YOUSSEF
Permit Cleared 1/14/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/14/2020 LEE GUILBEAUX
Sewer availability Cleared 1/14/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/14/2020 LEE GUILBEAUX

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/11/2020 Partial Approval MATTHEW NUCKOLLS
Deputy Drilled-In Anchors 5/20/2020 Conditional Approval DAVID CHAN
Excavation/Setback/Form/Re-Bar 5/28/2020 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2020 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Partial Approval DAVID CHAN
HVAC-Rough 7/10/2020 Approved DAVID CHAN
PLUMBING-Rough 7/15/2020 Approved DAVID CHAN
Shower Pan 7/20/2020 Approved DAVID CHAN
Deputy Wood Construction 7/22/2020 Conditional Approval SABAS ALONSO
Deputy Wood Construction 7/23/2020 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/24/2020 Not Ready for Inspection DAVID CHAN
Green Building Rough 7/24/2020 Approved DAVID CHAN
METHANE-Rough 7/24/2020 Approved DAVID CHAN
ELECTRICAL-Rough 7/29/2020 Approved DAVID CHAN
Insulation 8/4/2020 Approved DAVID CHAN
Interior/Exterior Lathing 8/10/2020 Not Ready for Inspection DAVID CHAN
Wood Frame 8/10/2020 No Access for Inspection DAVID CHAN
Interior/Exterior Lathing 8/13/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 8/19/2020 Conditional Approval DAVID CHAN
Drywall Nailing 8/21/2020 Approved SABAS ALONSO
Sewer 8/24/2020 Partial Approval DAVID CHAN
Interior/Exterior Lathing 8/31/2020 Approved DAVID CHAN
PLUMBING-Final 10/27/2020 Approved DAVID CHAN
ELECTRICAL-Final 10/28/2020 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 11/2/2020 Approved DAVID CHAN
HVAC-Final 11/2/2020 Approved DAVID CHAN
METHANE-Barrier 11/2/2020 Approved DAVID CHAN
METHANE-Subgrade 11/2/2020 Approved DAVID CHAN
Service/Power Release 11/2/2020 Approved DAVID CHAN
Final 11/24/2020 No Access for Inspection DAVID CHAN
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Not Ready DAVID CHAN
ELECTRICAL-Final 11/30/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 12/4/2020 Approved DAVID CHAN
Final 12/4/2020 Conditional Approval DAVID CHAN
Green Building Final 12/4/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 12/4/2020 SGSOV Approved DAVID CHAN
Smoke Detectors 12/4/2020 Approved DAVID CHAN
Final 12/14/2020 OK to Issue CofO DAVID CHAN