1809 S ARMACOST AVE 90025

Certificate Information: 1809 S ARMACOST AVE 90025

Application / Permit
19014-30000-06199
Plan Check / Job No.
B19WL06390
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition to an (E) 1-story SFD w/ (N) attached garage & roof trusses.
Permit Issued
Issued on 1/23/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2019 APPLICANT
Green Plans Picked Up 11/21/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 JAHANSHAH POURHASSAN
Corrections Issued 12/3/2019 JAHANSHAH POURHASSAN
Quality Review Completed 12/12/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/13/2019 APPLICANT
Applicant returned to address corrections 1/16/2020 JAHANSHAH POURHASSAN
Plan Check Approved 1/23/2020 JAHANSHAH POURHASSAN
Issued 1/23/2020 LADBS
CofO in Progress 6/24/2021 OGANES TARAKHCHYAN
Permit Finaled 7/2/2021 KENNETH NAGLE
CofO Issued 7/2/2021 KENNETH NAGLE
Permit Finaled 7/2/2021 KENNETH NAGLE

Permit Application Clearance Information

Trees in Parkway Cleared 12/21/2019 JOHN KIM
Green Code Cleared 1/9/2020 DONALD CRICHLOW
Eng Process Fee Ord 176,300 Cleared 1/14/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 1/14/2020 GEORGE SUCHAND
Low Impact Development Cleared 1/14/2020 SARAH YOUSSEF
Permit Cleared 1/14/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/14/2020 LEE GUILBEAUX
Sewer availability Cleared 1/14/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/14/2020 LEE GUILBEAUX

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620
Engineer Toedter,, Randy W; Lic. No.: S2991 7474 EISENHOWER ST      VENTURA, CA 93003

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/22/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 4/28/2020 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/5/2020 Approved OGANES TARAKHCHYAN
Sewer 5/18/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2020 Partial Approval ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 7/29/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Deputy Wood Construction 8/4/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/7/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/20/2020 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 9/8/2020 Approved OGANES TARAKHCHYAN
Shower Pan 9/11/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/16/2020 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/17/2020 Approved OGANES TARAKHCHYAN
HVAC-Rough 9/21/2020 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/22/2020 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/2/2020 No Access for Inspection KENNETH NAGLE
Green Building Rough 10/2/2020 No Access for Inspection KENNETH NAGLE
Wood Frame 10/6/2020 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/14/2020 Approved OGANES TARAKHCHYAN
Green Building Rough 10/14/2020 Approved OGANES TARAKHCHYAN
Insulation 2/2/2021 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 2/12/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/16/2021 Approved OGANES TARAKHCHYAN
Drywall Nailing 2/17/2021 Approved OGANES TARAKHCHYAN
Insulation 2/17/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 4/27/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 4/27/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 4/30/2021 Approved OGANES TARAKHCHYAN
Green Building Final 4/30/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 4/30/2021 Approved OGANES TARAKHCHYAN
Masonry Wall/Backfill 4/30/2021 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/30/2021 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 4/30/2021 Approved OGANES TARAKHCHYAN
Final 5/21/2021 Partial Inspection OGANES TARAKHCHYAN
HVAC-Final 5/21/2021 Approved OGANES TARAKHCHYAN
Service/Power Release 5/24/2021 Approved OGANES TARAKHCHYAN
Final 6/3/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 6/14/2021 Corrections Issued KENNETH NAGLE
PLUMBING-Final 6/16/2021 Approved KENNETH NAGLE
Final 6/24/2021 OK to Issue CofO OGANES TARAKHCHYAN