132 N KILKEA DR 90048
Certificate Information: 132 N KILKEA DR 90048
- Application / Permit
- 19014-30000-06083
- Plan Check / Job No.
- B19WL06275
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION TO EXISTING 1-STORY SFD.
- Permit Issued
- Issued on 2/6/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2019 | TARIK SAOUD |
| Corrections Issued | 11/25/2019 | TARIK SAOUD |
| Quality Review Completed | 11/26/2019 | FELIX FIGUEROA |
| Green Plans Picked Up | 11/26/2019 | APPLICANT |
| Building Plans Picked Up | 11/27/2019 | APPLICANT |
| Plan Check Approved | 1/6/2020 | TARIK SAOUD |
| Issued | 2/6/2020 | LADBS |
| CofO in Progress | 9/9/2021 | EVAN COOPER |
| Permit Finaled | 9/29/2021 | KENNETH NAGLE |
| CofO Issued | 9/29/2021 | KENNETH NAGLE |
| Permit Finaled | 9/29/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2019 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/2/2019 | ANTHONY MAINEZ |
| CPC | Cleared | 12/3/2019 | DENZEL HENDERSON |
| CPC | Cleared | 12/3/2019 | DENZEL HENDERSON |
| Green Code | Cleared | 12/11/2019 | RICHARD GARCIA |
| Low Impact Development | Cleared | 12/17/2019 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 12/17/2019 | JEANIE LAM |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 5919 S CROSFT AVENUE LOS ANGELES, CA 90056 |
| Contractor | Metco Group Inc; Lic. No.: 1037705-B | 1555 SAN YSIDRO DR BEVERLY HILLS, CA 90210 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/18/2020 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 4/7/2020 | Approved | EVAN COOPER |
| METHANE-Barrier | 4/7/2020 | Approved | EVAN COOPER |
| METHANE-Subgrade | 4/7/2020 | Approved | EVAN COOPER |
| Wood Frame | 4/7/2020 | Not Ready for Inspection | EVAN COOPER |
| Special/Order Compliance | 4/17/2020 | Corrections Issued | KENNETH NAGLE |
| Special/Order Compliance | 4/20/2020 | Partial Inspection | KENNETH NAGLE |
| BUILDING-Rough-Frame | 4/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 4/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Rough | 4/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Gas Test | 5/26/2020 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 5/26/2020 | Approved | EVAN COOPER |
| Sewer | 5/26/2020 | Approved | EVAN COOPER |
| HVAC-Rough | 7/24/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 7/30/2020 | Approved | EVAN COOPER |
| Gas Test | 7/30/2020 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 7/30/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 8/26/2020 | No Access for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 8/26/2020 | No Access for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2020 | No Access for Inspection | EVAN COOPER |
| Green Building Rough | 8/26/2020 | No Access for Inspection | EVAN COOPER |
| HVAC-Rough | 8/26/2020 | No Access for Inspection | EVAN COOPER |
| METHANE-Rough | 8/26/2020 | No Access for Inspection | EVAN COOPER |
| PLUMBING-Rough | 8/26/2020 | No Access for Inspection | EVAN COOPER |
| Wood Frame | 8/26/2020 | No Access for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 8/28/2020 | Partial Approval | EVAN COOPER |
| Green Building Rough | 8/28/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 8/28/2020 | Partial Approval | EVAN COOPER |
| METHANE-Rough | 8/28/2020 | Approved | EVAN COOPER |
| Wood Frame | 8/28/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Approved | EVAN COOPER |
| Insulation | 9/28/2020 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 9/28/2020 | Corrections Issued | EVAN COOPER |
| Insulation | 10/15/2020 | Approved | EVAN COOPER |
| Deputy Wood Construction | 10/20/2020 | Conditional Approval | EVAN COOPER |
| Deputy Wood Construction | 10/22/2020 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2020 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 10/30/2020 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/30/2020 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 10/30/2020 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 1/12/2021 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Final | 3/31/2021 | Approved | EVAN COOPER |
| Final | 3/31/2021 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 3/31/2021 | Approved | EVAN COOPER |
| Smoke Detectors | 3/31/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 4/27/2021 | Approved | EVAN COOPER |
| Final | 4/27/2021 | Corrections Issued | EVAN COOPER |
| Green Building Final | 4/27/2021 | Approved | EVAN COOPER |
| Green Building Rough | 4/27/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/27/2021 | SGSOV Approved | EVAN COOPER |
| Final | 6/14/2021 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 6/14/2021 | Not Ready for Inspection | EVAN COOPER |
| Final | 6/17/2021 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 6/17/2021 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 8/10/2021 | Approved | EVAN COOPER |
| Service/Power Release | 8/11/2021 | Approved | EVAN COOPER |
| Final | 9/9/2021 | OK to Issue CofO | EVAN COOPER |