132 N KILKEA DR 90048

Certificate Information: 132 N KILKEA DR 90048

Application / Permit
19014-30000-06083
Plan Check / Job No.
B19WL06275
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GROUND FLOOR ADDITION TO EXISTING 1-STORY SFD.
Permit Issued
Issued on 2/6/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2019 APPLICANT
Assigned to Plan Check Engineer 11/20/2019 TARIK SAOUD
Corrections Issued 11/25/2019 TARIK SAOUD
Quality Review Completed 11/26/2019 FELIX FIGUEROA
Green Plans Picked Up 11/26/2019 APPLICANT
Building Plans Picked Up 11/27/2019 APPLICANT
Plan Check Approved 1/6/2020 TARIK SAOUD
Issued 2/6/2020 LADBS
CofO in Progress 9/9/2021 EVAN COOPER
Permit Finaled 9/29/2021 KENNETH NAGLE
CofO Issued 9/29/2021 KENNETH NAGLE
Permit Finaled 9/29/2021 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/2/2019 ANTHONY MAINEZ
Sewer availability Cleared 12/2/2019 ANTHONY MAINEZ
CPC Cleared 12/3/2019 DENZEL HENDERSON
CPC Cleared 12/3/2019 DENZEL HENDERSON
Green Code Cleared 12/11/2019 RICHARD GARCIA
Low Impact Development Cleared 12/17/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 12/17/2019 JEANIE LAM

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: C35389 5919 S CROSFT AVENUE      LOS ANGELES, CA 90056
Contractor Metco Group Inc; Lic. No.: 1037705-B 1555 SAN YSIDRO DR      BEVERLY HILLS, CA 90210
Engineer Funk,, David Lyle; Lic. No.: S5421 319 MAIN STREET      EL SEGUNDO, CA 90245

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/18/2020 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 4/7/2020 Approved EVAN COOPER
METHANE-Barrier 4/7/2020 Approved EVAN COOPER
METHANE-Subgrade 4/7/2020 Approved EVAN COOPER
Wood Frame 4/7/2020 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 4/17/2020 Corrections Issued KENNETH NAGLE
Special/Order Compliance 4/20/2020 Partial Inspection KENNETH NAGLE
BUILDING-Rough-Frame 4/21/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/21/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 4/21/2020 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Rough 4/21/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 4/21/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Gas Test 5/26/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 5/26/2020 Approved EVAN COOPER
Sewer 5/26/2020 Approved EVAN COOPER
HVAC-Rough 7/24/2020 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 7/30/2020 Approved EVAN COOPER
Gas Test 7/30/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 7/30/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 8/26/2020 No Access for Inspection EVAN COOPER
ELECTRICAL-Rough 8/26/2020 No Access for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 8/26/2020 No Access for Inspection EVAN COOPER
Green Building Rough 8/26/2020 No Access for Inspection EVAN COOPER
HVAC-Rough 8/26/2020 No Access for Inspection EVAN COOPER
METHANE-Rough 8/26/2020 No Access for Inspection EVAN COOPER
PLUMBING-Rough 8/26/2020 No Access for Inspection EVAN COOPER
Wood Frame 8/26/2020 No Access for Inspection EVAN COOPER
BUILDING-Rough-Frame 8/28/2020 Partial Approval EVAN COOPER
Green Building Rough 8/28/2020 Not Ready for Inspection EVAN COOPER
HVAC-Rough 8/28/2020 Partial Approval EVAN COOPER
METHANE-Rough 8/28/2020 Approved EVAN COOPER
Wood Frame 8/28/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Approved EVAN COOPER
Insulation 9/28/2020 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 9/28/2020 Corrections Issued EVAN COOPER
Insulation 10/15/2020 Approved EVAN COOPER
Deputy Wood Construction 10/20/2020 Conditional Approval EVAN COOPER
Deputy Wood Construction 10/22/2020 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Partial Approval EVAN COOPER
Drywall Nailing 10/30/2020 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 10/30/2020 Partial Approval KEVIN SARGSYAN
Shower Pan 10/30/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 1/12/2021 Partial Approval EVAN COOPER
ELECTRICAL-Final 3/31/2021 Approved EVAN COOPER
Final 3/31/2021 Corrections Issued EVAN COOPER
PLUMBING-Final 3/31/2021 Approved EVAN COOPER
Smoke Detectors 3/31/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 4/27/2021 Approved EVAN COOPER
Final 4/27/2021 Corrections Issued EVAN COOPER
Green Building Final 4/27/2021 Approved EVAN COOPER
Green Building Rough 4/27/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/27/2021 SGSOV Approved EVAN COOPER
Final 6/14/2021 Not Ready for Inspection EVAN COOPER
Service/Power Release 6/14/2021 Not Ready for Inspection EVAN COOPER
Final 6/17/2021 Not Ready for Inspection EVAN COOPER
Service/Power Release 6/17/2021 Not Ready for Inspection EVAN COOPER
Service/Power Release 8/10/2021 Approved EVAN COOPER
Service/Power Release 8/11/2021 Approved EVAN COOPER
Final 9/9/2021 OK to Issue CofO EVAN COOPER