435 S LORRAINE BLVD 90020

Certificate Information: 435 S LORRAINE BLVD 90020

Application / Permit
19014-30000-06077
Plan Check / Job No.
B19WL06267
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADDITION TO (E) SFD. DEMO & REVISE ENTRANCE LAYOUT.
Permit Issued
Issued on 7/29/2020
Issuing Office
Current Status
CofO Issued on 2/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 VLADIMIR ARUTYUNYAN
Corrections Issued 11/15/2019 VLADIMIR ARUTYUNYAN
Plan Check Approved 7/29/2020 VLADIMIR ARUTYUNYAN
Issued 7/29/2020 APPLICANT
Building Plans Picked Up 8/4/2020 APPLICANT
CofO in Progress 10/19/2022 JEFFREY MEAD
Permit Finaled 2/22/2023 DANIEL ORRANTE
CofO Issued 2/22/2023 DANIEL ORRANTE
Permit Finaled 2/22/2023 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 12/3/2019 SARAH GOLDMAN
CPC Cleared 12/3/2019 SARAH GOLDMAN
CPC Cleared 12/3/2019 SARAH GOLDMAN
Eng Process Fee Ord 176,300 Cleared 12/3/2019 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 12/3/2019 ANTHONY MAINEZ
ZA Case Cleared 12/3/2019 SARAH GOLDMAN
HPOZ Cleared 1/15/2020 LYDIA CHAPMAN

Contact Information

Contractor Howley Lauren; Lic. No.: 1020130-B 4700 MASCOT STREET      LOS ANGELES, CA 90019
Engineer Peck,, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/26/2021 Approved STUART CHAPMAN
PLUMBING-Rough 4/21/2021 Partial Approval CHRIS CHRISTENSEN
Structural Steel Frame 4/21/2021 Partial Approval CHRIS CHRISTENSEN
Wood Frame 4/30/2021 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/7/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 5/7/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 5/7/2021 Approved CHRIS CHRISTENSEN
Structural Steel Frame 5/7/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/28/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 7/28/2021 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 7/28/2021 Approved CHRIS CHRISTENSEN
Wood Frame 7/28/2021 Partial Approval CHRIS CHRISTENSEN
Shower Pan 8/9/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/13/2021 Approved JOSEPH MCGARRY
HVAC-Rough 8/13/2021 Approved JOSEPH MCGARRY
Wood Frame 8/13/2021 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 8/18/2021 Partial Approval CHRIS CHRISTENSEN
Insulation 9/14/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 10/12/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/3/2021 Approved MASHEL JONGERT
BUILDING-Rough-Frame 8/17/2022 Approved JEFFREY MEAD
ELECTRICAL-Final 8/17/2022 Corrections Issued JEFFREY MEAD
Final 8/17/2022 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 8/17/2022 Approved JEFFREY MEAD
Green Building Final 8/17/2022 Approved JEFFREY MEAD
Green Building Rough 8/17/2022 Approved JEFFREY MEAD
METHANE-Barrier 8/17/2022 Approved JEFFREY MEAD
METHANE-Subgrade 8/17/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/17/2022 SGSOV Approved JEFFREY MEAD
Smoke Detectors 8/17/2022 Approved JEFFREY MEAD
Final 8/19/2022 Partial Approval JEFFREY MEAD
ELECTRICAL-Final 10/18/2022 Approved JEFFREY MEAD
Final 10/18/2022 OK to Issue CofO JEFFREY MEAD
HVAC-Final 10/18/2022 Approved JEFFREY MEAD
PLUMBING-Final 10/18/2022 Approved JEFFREY MEAD