1212 S BURNSIDE AVE 90019
Certificate Information: 1212 S BURNSIDE AVE 90019
- Application / Permit
- 19014-30000-06021
- Plan Check / Job No.
- B19WL06208
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and alteration to (E) single family dwelling with attached garage. Equipped with fire sprinkler system NFPA-13D.
- Permit Issued
- Issued on 1/9/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/5/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | ALFREDO JARA |
| Corrections Issued | 11/18/2019 | ALFREDO JARA |
| Green Plans Picked Up | 11/19/2019 | APPLICANT |
| Quality Review Completed | 11/27/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/2/2019 | APPLICANT |
| Plan Check Approved | 1/9/2020 | ALFREDO JARA |
| Issued | 1/9/2020 | LADBS |
| CofO in Progress | 10/24/2020 | DAVID CHAN |
| Permit Finaled | 11/5/2020 | DEROLD HAUFF |
| CofO Issued | 11/5/2020 | DEROLD HAUFF |
| Permit Finaled | 11/5/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 12/6/2019 | JOHN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2019 | ELENA LOPEZ |
| Low Impact Development | Cleared | 12/30/2019 | JORGE MEJIA LEMUS |
| Permit | Cleared | 12/30/2019 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 12/30/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 12/30/2019 | ELENA LOPEZ |
| Green Code | Cleared | 1/2/2020 | RICHARD GARCIA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/2/2020 | Partial Inspection | DAVID CHAN |
| Underground Mechanical | 3/2/2020 | Partial Inspection | DAVID CHAN |
| METHANE-Subgrade | 3/9/2020 | Partial Inspection | DAVID CHAN |
| METHANE-Barrier | 4/6/2020 | Approved | DAVID CHAN |
| Deputy Methane Barrier | 4/13/2020 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 4/17/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2020 | Approved | DAVID CHAN |
| Sewer | 4/29/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2020 | No Access for Inspection | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2020 | Approved | MATTHEW NUCKOLLS |
| HVAC-Rough | 5/21/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Rough | 5/26/2020 | Approved | DAVID CHAN |
| Deputy Wood Construction | 5/28/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 6/5/2020 | Corrections Issued | DAVID CHAN |
| PLUMBING-Rough | 6/10/2020 | Approved | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 6/12/2020 | Approved | DAVID CHAN |
| METHANE-Rough | 6/12/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 6/15/2020 | Conditional Approval | DAVID CHAN |
| Green Building Rough | 6/15/2020 | Approved | DAVID CHAN |
| Shower Pan | 6/17/2020 | Approved | SABAS ALONSO |
| Insulation | 6/18/2020 | Not Ready for Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 6/19/2020 | Approved | DAVID CHAN |
| Insulation | 6/19/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 6/26/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/30/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 7/6/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Final | 9/3/2020 | Approved | DAVID CHAN |
| Service/Power Release | 9/3/2020 | Approved | DAVID CHAN |
| HVAC-Final | 9/4/2020 | Approved | DAVID CHAN |
| Gas Test | 9/8/2020 | Approved | DAVID CHAN |
| PLUMBING-Final | 9/8/2020 | Approved | DAVID CHAN |
| Final | 9/22/2020 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 9/22/2020 | Approved | DAVID CHAN |
| Green Building Final | 9/22/2020 | Approved | DAVID CHAN |
| METHANE-Subgrade | 9/22/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2020 | SGSOV Approved | DAVID CHAN |
| Smoke Detectors | 9/22/2020 | Approved | DAVID CHAN |
| Final | 10/22/2020 | OK to Issue CofO | DAVID CHAN |