739 N GARDNER ST 90046
Certificate Information: 739 N GARDNER ST 90046
- Application / Permit
- 19014-30000-05967
- Plan Check / Job No.
- B19WL06154
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODELING AND (N) ADDITION TO (E) SFD
- Permit Issued
- Issued on 12/17/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | KAVIAN REFAHI |
| Corrections Issued | 11/7/2019 | KAVIAN REFAHI |
| Building Plans Picked Up | 11/15/2019 | APPLICANT |
| Plan Check Approved | 11/21/2019 | JAHANSHAH POURHASSAN |
| Issued | 12/17/2019 | LADBS |
| CofO in Progress | 8/24/2023 | SCOTT FINNILA |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2019 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 11/21/2019 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Barna Matthew F; Lic. No.: 985211-B | 34 WASHINGTON AVE RICHMOND, CA 94801 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 5525 CANOGA AVE APT 208 WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/20/2019 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/20/2019 | Approved | JOSEPH MCGARRY |
| METHANE-Barrier | 12/20/2019 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 12/20/2019 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/29/2020 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2020 | Partial Approval | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 7/30/2020 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 10/9/2020 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/9/2020 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 10/9/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/16/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 10/16/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/16/2020 | Partial Approval | CHRIS CHRISTENSEN |
| METHANE-Rough | 10/16/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/16/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 11/6/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 11/10/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/10/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 11/30/2020 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 12/15/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/15/2020 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 12/15/2020 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 11/17/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/17/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 11/17/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/17/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 11/17/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 11/17/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 11/17/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/17/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2021 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/17/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/16/2022 | Approved | MICHAEL LEWIS |
| Final | 11/16/2022 | Partial Inspection | MICHAEL LEWIS |
| HVAC-Final | 11/16/2022 | Conditional Approval | MICHAEL LEWIS |
| PLUMBING-Final | 11/16/2022 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | MICHAEL LEWIS |
| Special/Order Compliance | 6/26/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 8/24/2023 | OK to Issue CofO | SCOTT FINNILA |